Information based on query as of Tuesday, June 25, 2024.
Permit Information
Permit NumberESC16-00276
StatusFinaled
Name JILL JENKINS
Site Address 2421 N WILDWOOD ST
Project NameCay Subdivision
Customer Number 
ePlanReviewNo
Description
(Ustick Townsite)To conduct excavation of approximately cubic yards of earth to prepare for a new residential subdivision (future single family dwellings).
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection4/5/20174/7/20174/7/2017APASS
DetailsAndy J. Long
Subdivision work complete. Common areas vegetated. SFHs now in progress on Tahiti Street. ESC permits now with Wood Bros. for Eagle Energy Concepts. No futher ESC inspections on this permit.
DOC - Permit Finaled4/7/20174/7/20174/7/2017PPASS
DetailsAndy J. Long
General Inspection4/5/20174/5/20174/5/2017 CANC
DetailsAndy J. Long
General Inspection3/21/20173/21/20173/23/2017 CANC
DetailsAndy J. Long
General Inspection3/6/20173/6/20173/6/2017 PEND
DetailsAndy J. Long
Working on corrections with SFH builder Eagle Energy Concepts and Wood Bros. excavation to get regular sweeping schedule on Tahiti. Subdivision development complete.
General Inspection2/17/20172/17/20172/21/2017 CANC
DetailsMelissa Jannusch
General Inspection2/2/20172/2/20172/6/2017 CANC
DetailsAndy J. Long
General Inspection1/18/20171/18/20171/19/2017 CANC
DetailsAndy J. Long
General Inspection1/3/20171/3/20171/4/2017 CANC
DetailsAndy J. Long
General Inspection12/15/201612/15/201612/15/2016 CANC
DetailsAndy J. Long
General Inspection11/23/201611/30/201611/30/2016APASS
DetailsAndy J. Long
Subdivsion work complete and parcels ready for SFH construction. No SFH construction yet and lots are not permanently stabilized.

Notified by RP that insepction frequency will be decreased due to no activity, winter, and temporary stabilization of disturbed areas.

New subdivision storm drains have sediment filter mats installed, landscaping is common areas is complete, and graded areas have low runoff potential. No corrections needed at site.
General Inspection11/23/201611/23/201611/23/2016 CANC
DetailsAndy J. Long
rescheduled
General Inspection11/8/201611/8/201611/10/2016 CANC
DetailsAndy J. Long
General Inspection10/20/201610/21/201610/21/2016PCANC
DetailsAndy J. Long
General Inspection10/20/201610/20/201610/20/2016 CANC
DetailsAndy J. Long
rescheduled 10/21
General Inspection10/5/201610/5/201610/5/2016 CANC
DetailsAndy J. Long
General Inspection9/20/20169/20/20169/20/2016 PASS
DetailsAndy J. Long
Road and gutter installed. Entrance to subdivision off Wildwood has been landscaped and hydroseeded. Streets are clean. No SFH activity yet. New storm drain within subdivsion are fitted with filter mats on Silversage and Tahiti Street. No corrections needed at this time.
General Inspection9/1/20169/1/20169/1/2016 PASS
DetailsEvan Jenkins
Work is in Progress with no ESC issues observed.
Did no visually see any discharges leaving the site, including Fugitive Dust.
General Inspection8/12/20168/12/20168/12/2016PFAIL
DetailsEvan Jenkins
clicked on wrong inspection. will be there this afternoon.

Significant amount of trackout on Tahiti St. on sidewalks, curbs and street. Informed RP Jill to get this cleaned up. She stated she will. WIll follow up on Monday Morning
General Inspection8/12/20168/12/20168/12/2016PPASS
DetailsEvan Jenkins
SFH near completion.
No ESC issues observed at this time
General Inspection6/24/20166/24/20166/24/2016APASS
DetailsEvan Jenkins
No issues observed at time of inspection
General Inspection3/21/20163/29/20163/30/2016APASS
DetailsAndy J. Long
Road base area and parcels have been rough graded. No activity at time of inspection. Irrigation ditch tile and culvert is complete and ready for flow.

BMPs include permit signage, heavy construction entrance, and perimeter wattles on the north border of development.

No violations observed.
Site Preparation3/21/20163/21/20163/21/2016PPASS
DetailsAndy J. Long
Jill Phone #: ###-####

Permit sign and SWPPP information posted. Work within irrigation canal ROW has already occurred in order to tile the ditch prior to construction.

Initial BMPs installed. Will check back on conditions early next week. Approved to start.