General Inspection | 4/5/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Andy J. Long
|
|
|
Subdivision work complete. Common areas vegetated. SFHs now in progress on Tahiti Street. ESC permits now with Wood Bros. for Eagle Energy Concepts. No futher ESC inspections on this permit.
|
DOC - Permit Finaled | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/5/2017 | 4/5/2017 | 4/5/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/21/2017 | 3/21/2017 | 3/23/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/6/2017 | 3/6/2017 | 3/6/2017 | | PEND |
Andy J. Long
|
|
|
Working on corrections with SFH builder Eagle Energy Concepts and Wood Bros. excavation to get regular sweeping schedule on Tahiti. Subdivision development complete.
|
General Inspection | 2/17/2017 | 2/17/2017 | 2/21/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 2/2/2017 | 2/2/2017 | 2/6/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/18/2017 | 1/18/2017 | 1/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/3/2017 | 1/3/2017 | 1/4/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/15/2016 | 12/15/2016 | 12/15/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/23/2016 | 11/30/2016 | 11/30/2016 | A | PASS |
Andy J. Long
|
|
|
Subdivsion work complete and parcels ready for SFH construction. No SFH construction yet and lots are not permanently stabilized.
Notified by RP that insepction frequency will be decreased due to no activity, winter, and temporary stabilization of disturbed areas.
New subdivision storm drains have sediment filter mats installed, landscaping is common areas is complete, and graded areas have low runoff potential. No corrections needed at site.
|
General Inspection | 11/23/2016 | 11/23/2016 | 11/23/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 11/8/2016 | 11/8/2016 | 11/10/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/20/2016 | 10/21/2016 | 10/21/2016 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled 10/21
|
General Inspection | 10/5/2016 | 10/5/2016 | 10/5/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/20/2016 | 9/20/2016 | 9/20/2016 | | PASS |
Andy J. Long
|
|
|
Road and gutter installed. Entrance to subdivision off Wildwood has been landscaped and hydroseeded. Streets are clean. No SFH activity yet. New storm drain within subdivsion are fitted with filter mats on Silversage and Tahiti Street. No corrections needed at this time.
|
General Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | | PASS |
Evan Jenkins
|
|
|
Work is in Progress with no ESC issues observed. Did no visually see any discharges leaving the site, including Fugitive Dust.
|
General Inspection | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | FAIL |
Evan Jenkins
|
|
|
clicked on wrong inspection. will be there this afternoon.
Significant amount of trackout on Tahiti St. on sidewalks, curbs and street. Informed RP Jill to get this cleaned up. She stated she will. WIll follow up on Monday Morning
|
General Inspection | 8/12/2016 | 8/12/2016 | 8/12/2016 | P | PASS |
Evan Jenkins
|
|
|
SFH near completion. No ESC issues observed at this time
|
General Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Evan Jenkins
|
|
|
No issues observed at time of inspection
|
General Inspection | 3/21/2016 | 3/29/2016 | 3/30/2016 | A | PASS |
Andy J. Long
|
|
|
Road base area and parcels have been rough graded. No activity at time of inspection. Irrigation ditch tile and culvert is complete and ready for flow.
BMPs include permit signage, heavy construction entrance, and perimeter wattles on the north border of development.
No violations observed.
|
Site Preparation | 3/21/2016 | 3/21/2016 | 3/21/2016 | P | PASS |
Andy J. Long
|
|
|
Jill Phone #: ###-####
Permit sign and SWPPP information posted. Work within irrigation canal ROW has already occurred in order to tile the ditch prior to construction.
Initial BMPs installed. Will check back on conditions early next week. Approved to start.
|