Site Final | 10/11/2016 | 10/12/2016 | 10/12/2016 | A | PASS |
Andy J. Long
|
|
|
9:30 with Jason JEC and Dave with Inland
Final site walk through conducted. No work or BMPs offsite or in ROW. Staging yard area has been extended by grading pit run of geotextile for extended equipment and material storage.
Drainage ditch has been constructed and stormwater retention/infiltration pond excavated. No vegetation in pond due to potential fire danger and risk to construction yard.
No futher ESC inspections required, permit conditions satisfied. If yard expansion continues in future, new permits will be filed.
|
General Inspection | 9/2/2016 | 9/2/2016 | 9/2/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PASS |
Andy J. Long
|
|
|
No issues at site in industrial area. Warehouse has been erected. Waiting for stabilization in fall for better weather. SWPPP inspector to reduce inspection frequency to once per month.
|
Site Preparation | 3/22/2016 | 3/22/2016 | 3/22/2016 | P | PART |
Evan Jenkins
|
|
|
Jason Phone #: ###-####
Post Permit at Entrance Approved for construction
|