Permit NumberESC16-00310
StatusFinaled
Name PAT PALMER
Site Address 11064 W USTICK RD
Project NameGatehouse
Customer Number 
ePlanReviewNo
Description
Building #1 - West 9-Plex Townhome: One 4-plex building and two 9-plex townhome style buildings. A total of 22 units, the 2 downstairs units in the 4-plex will be ADA type A units. All 22 units will be 2 bedroom, 2 bathroom units and the 18 townhome style units will have the kitchen, living room and a powder bathroom downstairs with 2 bedrooms and 2 bathrooms upstairs. The project is located approximately 1,200 feet west of Five Mile Road on the north side of Ustick.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled11/29/201611/29/201611/29/2016PPASS
DetailsAndy J. Long
Gatehouse apartment building near completion. Site landscaped and cleaned. Some minor work on interiors. All vertical construction ESC permits closed, main subdivision site permit open, see ESC15-00547
General Inspection11/24/201611/24/201611/25/2016 CANC
DetailsAndy J. Long
General Inspection11/9/201611/9/201611/10/2016 CANC
DetailsAndy J. Long
General Inspection10/25/201610/25/201610/26/2016 PASS
DetailsAndy J. Long
General Inspection10/7/201610/7/201610/7/2016 PART
DetailsAndy J. Long
Site cleanup has continued and new site improvements of walk ways and curbing along entrance is in place.

Correction request to complete all clean up activity (sweeping, trash and debris pickup and haul off). N

NO trackout to Ustick, no discharges. Onsite inlets and MS4 now have sediment protection. See also main ESC permit for Gatehouse Sub.
ESC15-00547
BMP Violation9/20/20169/22/20169/22/2016ACANC
DetailsAndy J. Long
General Inspection9/9/20169/19/20169/20/2016PFAIL
DetailsAndy J. Long
Numerous violations and potential pollutants uncontained on site:

- no washout containment, piles and spills poured around in various areas and leaking into private storm drains installed for the site.
- litter, construction debris, sawdust, concrete, wall board dust all over parking lot and impermeable surfaces.
- dirt and sediment throughout parking lot. Ready to transport to MS4 on Ustick with no inlet bag
- stockpile stored on site has no perimeter controls and should be removed from site if it is not for use

Corrective actions needed ASAP

- clean up all litter and loose materials
- provide designated concrete washout that is lined and won't spill
- sweep up entrance way so that rain won;t carry dirt to Ustick
- remove all illicit concrete piles around site.
- sweep parking lot
- install sediment filter BMPs west of site on Ustick and on do service on all private inlets. Some are not even protected.

Re-inspection scheduled for Thursday AM
Random Inspection9/15/20169/15/20169/15/2016PPASS
DetailsScott Arellano
No track out observed.
General Inspection9/8/20169/9/20169/9/2016ACANC
DetailsAndy J. Long
rescheduled
General Inspection9/8/20169/8/20169/8/2016 CANC
DetailsAndy J. Long
rescheduled for 9/9