Site Final | 2/6/2017 | 2/6/2017 | 2/6/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 2/6/2017 | 2/6/2017 | 2/6/2017 | | PASS |
Melissa Jannusch
|
|
|
Final vegetation in place. Okay to final.
|
General Inspection | 1/19/2017 | 1/19/2017 | 1/19/2017 | | CANC |
Melissa Jannusch
|
|
|
No changes since last inspection. Snow covered conditions
|
General Inspection | 1/4/2017 | 1/4/2017 | 1/5/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/16/2016 | 12/16/2016 | 12/19/2016 | | PEND |
Andy J. Long
|
|
|
Construction complete but need to check landscaping and rear hillside BMP replacement for upper section of Somerset Village. No corrections issued at this time due to frozen conditions
|
General Inspection | 12/1/2016 | 12/1/2016 | 12/2/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/16/2016 | 11/16/2016 | 11/16/2016 | | PEND |
Andy J. Long
|
|
|
WIP on landscaping and interior work. Correction request previously issued to stabilize equipment access path behind home from Somerset #3 and reinstall silt fence and/or wattles. This is to be completed after landscaping and fence is installed.
|
General Inspection | 10/28/2016 | 10/28/2016 | 10/28/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/13/2016 | 10/13/2016 | 10/13/2016 | | CANC |
Andy J. Long
|
|
|
No issues observed at Somerset Village during inspections on 10/12. No precipitation received in the meanwhile.
|
General Inspection | 9/21/2016 | 9/21/2016 | 9/21/2016 | | PASS |
Andy J. Long
|
|
|
Not yet landscaped. WIP on interior/exterior finishes. No trackout or spills leaving site. Trash contained.
|
Site Preparation | 4/22/2016 | 4/22/2016 | 4/22/2016 | P | PART |
Evan Jenkins
|
|
|
Justin Phone #: ###-####
Permit Posted with straw waddles staked along front of lot. some minor discharge along front of construction lot that needs to be swept up. Approved for construction Will follow up monday to ensure sediment has been swept up
|