General Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 | | PASS |
Andy J. Long
|
|
|
Site work complete. Access roads and utilities are installed. Newly installed site stormwater system was fitted with DI filter bags.
Two seperate projects are now active at Emerald Station, Cascadia Healthcare ESC16-00676 and SARMC Emerald Clinic ESC16-01580, no further inspections required on this permit, permit finaled.
|
DOC - Permit Finaled | 4/10/2017 | 4/10/2017 | 4/10/2017 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/22/2017 | 2/22/2017 | 2/23/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP on foundations. BMPs in place. No trackout. No corrections requested
|
General Inspection | 1/4/2017 | 1/4/2017 | 1/5/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/18/2016 | 11/18/2016 | 11/18/2016 | | PASS |
Andy J. Long
|
|
|
Construction complete on access roads for Emerald Station as well as grading and site work. New project on the southwest parcel is in progress. See ESC16-00676
|
General Inspection | 9/30/2016 | 9/30/2016 | 9/30/2016 | | PASS |
Andy J. Long
|
|
|
No activity. Access roads and utilities installed. Some equipment and stockpiles on site. MS4 inlets on Curtis, Emerald and Denton have sediment bag protection. No trackoout or wind blown dust occuring. Will need further stabilization to have ESC final.
|
General Inspection | 7/27/2016 | 7/27/2016 | 7/27/2016 | P | PASS |
Andy J. Long
|
|
|
Emerald village road base work and sidewalk base work is in progress. SWPPP & Boise ESC permit onsite. Water truck on site for dust control, not in use at time of inspection. No plumes leaving work area/no complaints received. DIs have sediment bags installed and in good condition. No trackout to Curtis or Emerald. No corrections requested.
|
General Inspection | 6/28/2016 | 6/28/2016 | 6/28/2016 | P | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Underground utilities are installed but no roads, sidewalks or other surface features. BMPs for project installed. No windblown dust observed during inspection, no trackout or other issues. Approved.
|
Site Preparation | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | PASS |
Andy J. Long
|
|
|
Follow up inspection -
Construction entrance installed with heavy rock and geotextile lining. Permit sign postedl Stockpile has been tacified.
Approved.
|
Site Preparation | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PASS |
Andy J. Long
|
|
|
Michelle Phone #: ###-####
RP reviewed dust control and track out prevention /clean up with crew this morning. Permit sign posted near job trailer. SWPPP map updated with location of stockpile. Storm drains have inlet protection.
Approved for construction, starting today.
Note: onsite foreman is Vicente
|