General Inspection | 6/1/2017 | 6/1/2017 | 6/2/2017 | | PASS |
Andy J. Long
|
|
|
Home complete, occupied, stabilized/landscaped. BLD permit finaled with geotech approval. No ESC corrections or requests. Permit finaled.
|
DOC - Permit Finaled | 6/2/2017 | 6/2/2017 | 6/2/2017 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 5/4/2017 | 5/4/2017 | 5/4/2017 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 4/18/2017 | 4/19/2017 | 4/21/2017 | P | PASS |
Andy J. Long
|
|
|
Trackout observed previous inspection has been cleaned up and street has been swept.
Landscaping in progress for stabilization. Project near completion. No new corrections requested.
|
General Inspection | 4/18/2017 | 4/18/2017 | 4/18/2017 | | FAIL |
Andy J. Long
|
|
|
Trackout all over road in front of home due to landscaping crew driving in muddy areas.
Verbal Correction Request to clean up all trackout. Follow 4/19
|
General Inspection | 4/3/2017 | 4/3/2017 | 4/3/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/17/2017 | 3/17/2017 | 3/17/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 3/2/2017 | 3/2/2017 | 3/6/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/10/2017 | 2/15/2017 | 2/15/2017 | P | PASS |
Melissa Jannusch
|
|
|
Vertical WIP. No track out. BMPs are in place.
|
General Inspection | 2/10/2017 | 2/10/2017 | 2/10/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 1/26/2017 | 1/26/2017 | 1/30/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/9/2017 | 1/9/2017 | 1/11/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/21/2016 | 12/21/2016 | 12/29/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on frame and interior. Yellow permit sign posted. NO trackout or discharges from site. No erosion rills or sediment runoff points observed. Rock retaining wall now installed. No corrections requested.
|
General Inspection | 10/14/2016 | 10/14/2016 | 10/14/2016 | A | PASS |
Daryl DeGrange
|
|
|
Permit sign posted,no sediment runoff
|
General Inspection | 7/28/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Andy J. Long
|
|
|
Foundation complete and site was cleaned afterward. Trash container installed for framers, no sediment runoff. No perimeter wattle currently, may need to install if runoff occurs.
|
Site Preparation | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PASS |
Andy J. Long
|
|
|
Site meeting with J&H. Perimeter wattle installed at low end of lot. Will install construction entrance after excavation. Downstream storm drain has sediment filter mat. Permit sign posted. Approved for construction.
|