Site Final | 12/2/2016 | 12/2/2016 | 12/2/2016 | P | PASS |
Andy J. Long
|
|
|
Paving and stormwater management project complete. No disturbed area or loose construciton materials on site. No temporary BMPs remain installed. ESC permit conditions satisfied.
|
Site Preparation | 8/10/2016 | 8/11/2016 | 8/11/2016 | A | PASS |
Andy J. Long
|
|
|
Jason Phone #: ###-####
MS4 inlets on Pasadena and within HOA have inlet filter bags installed. Permit box and sign located on Pasadena. Flat terrain; scope of work does not include major grading or utility installation. RP to schedule Site Final and remove all temp BMPs upon completion.
|