General Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 12/7/2017 | 12/7/2017 | 12/7/2017 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 11/22/2017 | 11/22/2017 | 11/22/2017 | | PASS |
Michael Zawacki
|
|
|
Landscaping in progress
|
General Inspection | 11/7/2017 | 11/7/2017 | 11/7/2017 | P | PASS |
Michael Zawacki
|
|
|
Landscaping not complete.
|
General Inspection | 10/27/2017 | 10/27/2017 | 10/31/2017 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/12/2017 | 10/12/2017 | 10/12/2017 | | PASS |
Andy J. Long
|
|
|
Home is occupied, BLD finaled. Front yard is landscaped, WIP on backyard. DI bag still installed on Millet. No trackout or discharges observed.
|
General Inspection | 9/27/2017 | 9/27/2017 | 10/2/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/12/2017 | 9/12/2017 | 9/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/28/2017 | 8/28/2017 | 8/31/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/11/2017 | 8/11/2017 | 8/14/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/21/2017 | 7/27/2017 | 7/28/2017 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/21/2017 | 7/21/2017 | 7/21/2017 | | PASS |
Andy J. Long
|
|
|
Landscaping in progress. Some loose dirt on sidewalk and gutter will need sweeping. DI bag installed.
|
General Inspection | 7/6/2017 | 7/6/2017 | 7/6/2017 | | PASS |
Melissa Jannusch
|
|
|
No ESC issues observed.
|
General Inspection | 6/21/2017 | 6/21/2017 | 6/21/2017 | | PASS |
Melissa Jannusch
|
|
|
Nearing completion. No landscaping installed yet.
|
General Inspection | 6/6/2017 | 6/6/2017 | 6/6/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP. No trackout trash is contained. No Corrections requested.
|
General Inspection | 5/22/2017 | 5/22/2017 | 5/22/2017 | | PASS |
Melissa Jannusch
|
|
|
DI bag is clogged. Verticle WIP. No landscaping.
|
General Inspection | 5/5/2017 | 5/5/2017 | 5/5/2017 | | PEND |
Melissa Jannusch
|
|
|
Large stockpiles need protection/stabilization. No other ESC issues.
|
General Inspection | 4/20/2017 | 4/20/2017 | 4/20/2017 | | PASS |
Melissa Jannusch
|
|
|
No significant trackout. No other corrections
|
Tracking Control | 3/29/2017 | 4/5/2017 | 4/4/2017 | A | PASS |
Melissa Jannusch
|
|
|
Trash and dirt removed from gutter. Sidewalks need to be swept after sidewalk work is complete.
|
Tracking Control | 3/28/2017 | 3/29/2017 | 3/29/2017 | A | PEND |
Melissa Jannusch
|
|
|
Dirt in road and trash in gutter. Correction requested: clean up dirt and trash. Talked with RP.
|
General Inspection | 3/15/2017 | 3/15/2017 | 3/15/2017 | | PASS |
Melissa Jannusch
|
|
|
WIP. Small amount of trackout. Project ok.
|
General Inspection | 2/24/2017 | 2/24/2017 | 2/24/2017 | | PASS |
Melissa Jannusch
|
|
|
No corrections
|
General Inspection | 1/31/2017 | 2/9/2017 | 2/10/2017 | P | PART |
Melissa Jannusch
|
|
|
Track out has been addressed. Construction entrance is paved and cleaned. DI bags are still full. Corrections addressed: Track out, construction entrance Corrections still needed: DI bags on both sides of Millett Dr. need to be emptied
|
General Inspection | 1/31/2017 | 1/31/2017 | 1/31/2017 | | PART |
Melissa Jannusch
|
|
|
WIP on house. Wattles installed correctly and holding back some sediment. Sign is posted and visible. Small amounts of trash, but contained within the site. No track out.
Correction request: DI bag on Millet St. is full to the top. Left voice message for Chauncey Saunders (RP) requesting he clean the DI bag. Will follow up next week.
|
General Inspection | 11/29/2016 | 11/29/2016 | 11/29/2016 | P | PASS |
Andy J. Long
|
|
|
WIP. Permit sign posted. Driveway, no trackout from site perimeter on Woodcross. Wattle installed at bottom of site in good condition. No corrections requested.
|
Random Inspection | 11/1/2016 | 11/1/2016 | 11/1/2016 | A | PASS |
Andy J. Long
|
|
|
WIP on foundation. No activity at time of inspection. No significant trackout. Wattles along bottom of site installed, permit posted.
|
General Inspection | 9/29/2016 | 9/29/2016 | 9/29/2016 | A | PASS |
Andy J. Long
|
|
|
WIP on foundation and utility work. Crew on site watering area of excavation to keep dust down. Perimeter wattles installed and undisturbed. Permit posted. Approved.
|
General Inspection | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Andy J. Long
|
|
|
Foundation work occuring. Stockpiles of backfill are stored on lot. No loose dirt or other materials on sidewalk or gutter. DI bag installed, permit sign posted. Wattle installed a bottom of slope below new home. Approved.
|
Site Preparation | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | PASS |
Andy J. Long
|
|
|
Dirk Phone #: ###-####
Permit sign posted on porta-pot. Heavy duty straw wattle installed along bottom of slope on lot, below that is grassy strip and pathway. Low runoff potential on sidewalk border , RP & GC familiar with ESC conditions. DI bag from previous project is still installed, will need mainteance check next inspection .
Approved for excavation/construction.
|
General Inspection | 1/12/2017 | 1/12/2017 | | | |
Andy J. Long
|
|
|
|