Site Final | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Jim Sly
|
|
|
|
DOC - Permit Finaled | 10/20/2017 | 10/20/2017 | 10/20/2017 | P | PASS |
Jim Sly
|
|
|
|
General Inspection | 10/13/2017 | 10/13/2017 | 10/13/2017 | | PASS |
Andy J. Long
|
|
|
Near completion. Need to remove inlet bags from MS4 storm drains on Fairview and Gordon
|
General Inspection | 8/28/2017 | 8/28/2017 | 8/28/2017 | A | PASS |
Andy J. Long
|
|
|
Project near completion. Working on interior and parking lot entrance. No trackout or discharges of observed. Not yet landscaped but edge of sidewalk pavement is above grade of disturbed area, containing sediment. DI bags on Fairview still installed. Must be removed to get ESC final.
|
General Inspection | 7/26/2017 | 7/26/2017 | 7/27/2017 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/8/2017 | 6/8/2017 | 6/8/2017 | A | PASS |
Andy J. Long
|
|
|
Site work in progress. Receivnig storm drains on Fairview have sediment protection. Permit sign posted. No trackout or discharges. No dust observed, no complaints reported.
|
General Inspection | 4/7/2017 | 4/18/2017 | 4/17/2017 | P | PASS |
Andy J. Long
|
|
|
WIP. Old building demolished, site work and excavation for new building ready to start. BMPs installed. Approved.
|
General Inspection | 4/7/2017 | 4/7/2017 | 4/7/2017 | P | PASS |
Andy J. Long
|
|
|
Building demolished. MS4 inlets have sediment protection. No trackout or sediment runoff observed. Permit sign posted. Need to check on stabilization or perimeter sediment controls next inspection.
|
Site Preparation | 3/24/2017 | 3/27/2017 | 3/27/2017 | P | PASS |
Melissa Jannusch
|
|
|
Met with RP on site. Discussed CoB ESC protocol for inspections concrete washout, trackout control, dust control, and trash containment. Flat site. Sign posted. DI bags installed. Okay to start.
|