Site Final | 1/14/2019 | 1/15/2019 | 1/16/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/14/2019 | 1/14/2019 | 1/14/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Michael Zawacki
|
|
|
All work looks complete. Area landscaped and parking lot completed. No more materials stored on site.
|
Random Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on exterior finish, site is not yet fully landscaped, but stockpiles and dirt are not in road and gutter and have been pulled inward from the curb. No trackout or loose trash observed around perimeter.
|
General Inspection | 9/20/2018 | 9/25/2018 | 9/27/2018 | P | PASS |
Andy J. Long
|
|
|
Follow up inspection to check on mud in gutter on Pasadena
Gutter and sidewalk on Pasadena have been cleaned up as requested. No other violations. Project near completion, WIP on interiors and landscaping. Some units occupied.
|
Random Inspection | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | FAIL |
Andy J. Long
|
|
|
Mud in gutter on Pasadena Street needs to be cleaned up ASAP.
Verbarl correction request to RP Jeremy. Follow up scheduled for next week. Storm drain has sediment protection, dry conditions. No other violations.
|
General Inspection | 8/7/2018 | 8/7/2018 | 8/7/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 6/22/2018 | 6/22/2018 | 6/22/2018 | | CANC |
Andy J. Long
|
|
|
|
BMP Violation | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PART |
Andy J. Long
|
|
|
Permit posted, no loose trash around site. No spills or discharges occuring.
Corrections still needed: - RP stated sediment control protection has been purchased, but it still needs to be installed. - fix trash container so it has four walls.
|
General Inspection | 5/7/2018 | 5/7/2018 | 5/7/2018 | | PASS |
Andy J. Long
|
|
|
WIP on framing. Perimter curb and gutter currently be installed around site on Pasadena and Owhyee. SWPPP onsite. No trackout, no uncontained trash. No corrections requested.
|
General Inspection | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PEND |
Michael Zawacki
|
|
|
Two exits and neither are stabalized. Some trackout, called RP Jeremy and asked for repairs and cleaning. Rest of site is contained and clean, trash was being removed while I was on site.
|
General Inspection | 2/5/2018 | 2/5/2018 | 2/5/2018 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/11/2018 | 1/11/2018 | 1/11/2018 | P | PASS |
Michael Zawacki
|
|
|
WIP. Stockpiles on site. Dirt on Pasadena, some is from recent utility trenching. Owyhee is free from trackout. DI has blocksomm and witches hat. Fueling truck was on site, has all spill control and cleanup on board.
|
General Inspection | 12/19/2017 | 12/19/2017 | 12/19/2017 | | PASS |
Michael Zawacki
|
|
|
Stockpiles are removed. Dis have protection and are clean. Construction entrance in use. Concrete washout on site and being used. Few foundations in place, working on sewer lines.
|
Random Inspection | 11/3/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Michael Zawacki
|
|
|
DIs protected. Entire area graded, massive piles of dirt in middle of lot. Perimeter not protected yet.
|
Conference | 10/9/2017 | 10/10/2017 | 10/10/2017 | P | PASS |
Andy J. Long
|
|
|
Jeremy ###-####
Preconstruction conference with Biltmore RP at site. Grading to begin within 2-3 weeks, permit not yet issued.
Will install heavy duty construction entrance on Owyhee @ SW corner of parcel. Fiber mat protection on two storm drains on Pasadena and 1 DI bag on Owyhee. Fugitive dust control and water truck must be onsite with designated driver. Okay to wait on perimeter controls after initial grading begins.
CGP filed, eNOI tracking # IDR1000B2. Post SWPPP info and Boise ESC permit sign.
|