Aging Inspection | 3/7/2018 | 3/7/2018 | 3/7/2018 | | PASS |
Andy J. Long
|
|
|
Home complete and landscaped. ESC permit conditions satisfied. 3 projects in a row by Hill Construction. 1 permit remains open for DI bag removal east of sites on Poplar.
|
DOC - Permit Finaled | 3/7/2018 | 3/7/2018 | 3/7/2018 | P | PASS |
Andy J. Long
|
|
|
|
Aging Inspection | 1/4/2018 | 1/4/2018 | 1/4/2018 | | PASS |
Michael Zawacki
|
|
|
Work about complete. Some interior and garage work remaining.
|
Site Preparation | 4/4/2017 | 4/4/2017 | 4/4/2017 | P | PASS |
Andy J. Long
|
|
|
Dean Phone #: ###-####
Permit signs posted at site. Concrete washout bin provided onsite. RP-GC on site for inspection. Storm drain inlet to the east on Poplar will have filter mat installed. Driveways will be installed on alley, no new curb cutting
|