DOC - Permit Finaled | 11/1/2017 | 11/1/2017 | 11/1/2017 | P | PASS |
Michael Zawacki
|
|
|
|
Site Final | 10/2/2017 | 10/12/2017 | 10/16/2017 | P | PEND |
Michael Zawacki
|
|
|
WIP. Very clean, BMPs installed and used correctly.
|
General Inspection | 10/2/2017 | 10/2/2017 | 10/2/2017 | P | PASS |
Andy J. Long
|
|
|
WIP. Near completion. Site landscaping in progress. Need to remove temp DI bags in front of site upon completion and stabilize the adjacent lot used for staging. Will check for site final next week.
No trackout or discharges from site.
|
General Inspection | 6/21/2017 | 7/6/2017 | 7/10/2017 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation and walls. Construction entrance, inlet protection, permit sign posted,
No discharges, trackout, or fugitive dust observed.
|
Site Preparation | 6/19/2017 | 6/20/2017 | 6/21/2017 | A | CANC |
Andy J. Long
|
|
|
data entry error
|
General Inspection | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Andy J. Long
|
|
|
No trackout from site. Water truck onsite to control dust as necessary. DI bags installed.
Corrective action to trench in wattles on the south construction limit was completed. Work is occuring in this area currently. Need to sweep sidewalk once work in that area is complete.
|
General Inspection | 6/15/2017 | 6/16/2017 | 6/19/2017 | A | CANC |
Melissa Jannusch
|
|
|
follow up inspection; check wattles
|
Site Preparation | 6/12/2017 | 6/13/2017 | 6/13/2017 | A | PART |
Andy J. Long
|
|
|
Dave Phone #: ###-####
Permit sign posted, heavy duty construction entrance installed, perimeter sediment control wattle installed. Construction in progress.
Corrections needed: - trench in wattles on south side of site and clean up dirt on sidewalk. - provide concrete washout.
Will check for corrections on Friday.
Note - significant trackout from patrons of Del Taco, Dutch Bros, and Sonic on Overland due to unfenced vacant development lot on Ardene. Notified ACHD, case pending
|