DOC - Permit Finaled | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 7/27/2018 | 7/27/2018 | 7/27/2018 | | PART |
Michael Zawacki
|
|
|
Working on stucco. Some material buckets and waste laying around home.
|
General Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | | PASS |
Michael Zawacki
|
|
|
Home prepped for stucco. Trash removal company on site cleaning out trash box.
|
General Inspection | 6/27/2018 | 6/27/2018 | 6/27/2018 | | PART |
Michael Zawacki
|
|
|
Lots of garbage and stucco waste on site. This home hasn't started stucco work, is from neighboring home, same builder. Needs trash picked up and a stucco washout for when that work begins.
|
General Inspection | 6/12/2018 | 6/12/2018 | 6/12/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/28/2018 | 5/28/2018 | 5/29/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/10/2018 | 5/10/2018 | 5/10/2018 | | PASS |
Michael Zawacki
|
|
|
Some exterior painting and/or stucco work rmains. Landscape crew on site.
|
General Inspection | 4/25/2018 | 4/25/2018 | 4/25/2018 | | PASS |
Michael Zawacki
|
|
|
Framing has just begun. Site is clean and contained.
|
General Inspection | 4/6/2018 | 4/6/2018 | 4/6/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/16/2018 | 3/16/2018 | 3/16/2018 | | CANC |
Andy J. Long
|
|
|
|
Complaint Inspection | 8/18/2017 | 8/22/2017 | 8/25/2017 | P | PEND |
Andy J. Long
|
|
|
check on DI bag and concrete cutting fugitive dust
|
General Inspection | 8/7/2017 | 8/10/2017 | 8/18/2017 | P | PEND |
Andy J. Long
|
|
|
follow up
|
Site Preparation | 8/4/2017 | 8/7/2017 | 8/7/2017 | A | PART |
Andy J. Long
|
|
|
Clint Phone #: ###-####
Permit sign posted. Need to install DI protection on south side of Taboo culdesac before excavation.
Verbal correction to Clint.
|