Aging Inspection | 5/31/2018 | 5/31/2018 | 5/31/2018 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 5/31/2018 | 5/31/2018 | 5/31/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/24/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Andy J. Long
|
|
|
WIP. No trackout from site. Storm drains protected on Melrose. Workers parking on the street to avoid tracking. Permit sign posted.
|
General Inspection | 11/27/2017 | 11/27/2017 | 11/27/2017 | P | PASS |
Michael Zawacki
|
|
|
WIP on steel frame. All building is below level of road. New enterance and exit, some light tracking out of western exit. DIs are clean.
|
Random Inspection | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | PASS |
Michael Zawacki
|
|
|
Zfoundation poured. Vertical construction anticipated to begin this week. Site is below grade. Owner has placed new rock for entrance.
|
Site Preparation | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | PASS |
Andy J. Long
|
|
|
Ed Phone #: ###-####
BMPs installed. Permit sign posted. Rock construction entrance. Site drainage is towards northern end of lot away from Melrose. MS4 inlet has sediment bag installed. Approved for construction.
|