Site Final | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Andy J. Long
|
|
|
Pathway complete. Disturbed areas stabilized. No stockpiles or temporary BMPs left on site. Warm Springs Creek permitted seperately, see ESC17-00774
ESC permit conditions satisfied.
|
General Inspection | 3/29/2018 | 3/29/2018 | 4/5/2018 | P | PASS |
Andy J. Long
|
|
|
Pathway complete. Revegetation phase where path crosses Warm Springs Creek.
|
General Inspection | 1/5/2018 | 1/9/2018 | 1/10/2018 | P | PEND |
Andy J. Long
|
|
|
check with PW engineering on rip rap & culverts
|
General Inspection | 1/5/2018 | 1/5/2018 | 1/5/2018 | P | PEND |
Andy J. Long
|
|
|
Need to check on creek bed stabilization. Rip rap installed. No lining or seeding evident. Currently snow covered. Pathway is complete between Barber Drive and Millbrook now.
|
General Inspection | 11/20/2017 | 11/20/2017 | 11/20/2017 | A | PEND |
Michael Zawacki
|
|
|
Pathwy has been paved. Still exposed areas and stockpiles. Creek channel has no stabalization on bottom or sides.
|
General Inspection | 11/2/2017 | 11/2/2017 | 11/3/2017 | P | PEND |
Andy J. Long
|
|
|
WIP on channel relocation project. All TRM, erosion control blankets and jute matting are installed, staked in and and overlapping per specs. Some areas of tenting observed, but appears to be in good contact with the ground. Supplemental irrigation line is being installed, next week live willow cuttings are to be planted, and then bank areas and flat areas on the side of the creek channel will be hydroseeded/tacified.
|