Site Final | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | PASS |
Michael Zawacki
|
|
|
close out this permit and use ESC18-00031 for rest of project
|
General Inspection | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | FAIL |
Michael Zawacki
|
|
|
Lots of dirt in parking lot in work area being tracked onto Cory Ln. Excavator in back of site looks to be cause. Concrete washout is nearly full, will need to be maintained soon.
|
BMP Violation | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PEND |
Michael Zawacki
|
|
|
Failed washout. Contacted RP, parcel hold and reinspection fee if not clean at time of inspection. Talked with Andy has cleaned site, washout not done, will be later today. Check on 11-14
|
BMP Violation | 11/13/2018 | 11/14/2018 | 11/13/2018 | A | CANC |
Michael Zawacki
|
|
|
|
BMP Violation | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | CANC |
Michael Zawacki
|
|
|
Failed washout. Contacted RP, parcel hold and reinspection fee if not clean at time of inspection. Talked with Andy has cleaned site, washout not done, will be later today. Check on 11-14
|
General Inspection | 10/10/2018 | 10/10/2018 | 10/10/2018 | P | PART |
Michael Zawacki
|
|
|
No new work has begun. Dirt ramps have been built into the parking lot. No dirt leaving site, lots in parking lot going to sites storm drain system.
|
General Inspection | 8/22/2018 | 9/5/2018 | 9/5/2018 | P | PART |
Andy J. Long
|
|
|
check for activity and removal of dirt ramps in parking lot
No new activity, no changes at site. Notified RP that the dirt ramps will want to be removed prior to starting the excavation for the foundation to keep the parking lot from becoming dirty and a source of trackout to Cory.
|
General Inspection | 8/21/2018 | 8/21/2018 | 8/22/2018 | | PART |
Andy J. Long
|
|
|
No trackout or offsite discharges, but dirt ramps within subdivsion will get the parking lot surface very dirty.
Request to remove dirt ramps before end of month.
|
General Inspection | 6/8/2018 | 6/8/2018 | 6/8/2018 | P | PASS |
Michael Zawacki
|
|
|
Site is contained. Curba and parking lot completed. Dirt ramps leading of parking lot, lots of runoff onto parking lot. Inlets on site are protected.
|
General Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Michael Zawacki
|
|
|
Sidewalks, parking lot, curb & gutter completed. Most of irragation ditch has been piped, junctions still not complete. No dirt leaving site. No activity at time of inspection.
|
Random Inspection | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Michael Zawacki
|
|
|
No workers on site. No mud coming off site.
|
Tracking Control | 1/12/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Michael Zawacki
|
|
|
Street has been swept. Talked to RP Andy, they will get new perimeter BMPs and figure out placement for construction entrance.
|
General Inspection | 10/23/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Michael Zawacki
|
|
|
Perimeter controls intact. No material has left site. Stockpiles are on site. Entrance is not rock, will need to monitor over construction.
|
Site Preparation | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Andy J. Long
|
|
|
1 PM
Onsite inspection with RP-GC Andy. Permit sign posted; perimeter wattles and vegetated strip left to contain site. Excavator to install construction entrance. Storm drain west of site has inlet protection. Top soil layer has been grubbed and is stockplile in back corner. Irrigation ditch is dry for winter season and will be tiled with 10" pipe.
Approved for construciton, no vertical construction. BLD permits for units to submitted soon.
|
Site Preparation | 10/19/2017 | 10/20/2017 | 10/23/2017 | A | CANC |
Andy J. Long
|
|
|
rescheduled
|