Site Final | 7/17/2018 | 8/7/2018 | 8/8/2018 | A | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Andy J. Long
|
|
|
Home near completion. Yard has been landscaped with trees and sod, disturbed slopes around the perimeter have been hydroseeded. No violations observed.
|
Tracking Control | 3/21/2018 | 3/27/2018 | 3/27/2018 | A | PEND |
Michael Zawacki
|
|
|
Currently on site fixing entrance.
|
Tracking Control | 3/20/2018 | 3/21/2018 | 3/21/2018 | A | PEND |
Michael Zawacki
|
|
|
Talked to dave with Canyon Crest Homes. He is aware that entrance is bad, said gas company caused issue with line install. Has cleanup and new rock scheduled for 3/22. Will follow up next week.
|
General Inspection | 2/1/2018 | 2/6/2018 | 2/9/2018 | A | PEND |
Andy J. Long
|
|
|
check for construction entrance.
|
Site Preparation | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Andy J. Long
|
|
|
Dave Phone #: ###-####
ESC permit posted. Perimeter wattles installed around site. EC phas 8 has storm drains fitted with sediment bags.
Construction entrance not yet installed, notified RP that it is required and follow up inspection scheduled for early next week.
|