DOC - Permit Finaled | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Andy J. Long
|
|
|
see ESC17-01754 for rest of Skyline ESC activities
|
General Inspection | 5/13/2019 | 5/13/2019 | 5/13/2019 | | PASS |
Michael Zawacki
|
|
|
Interior road bed prep un derway. Washout and dumpster on site. Site is clean and trash picked up. Landscaping completed along 2/3 of Federal way.
|
General Inspection | 3/26/2019 | 3/26/2019 | 3/26/2019 | | CANC |
Andy J. Long
|
|
|
see ESC17-01754
|
General Inspection | 2/8/2019 | 2/8/2019 | 2/8/2019 | | FAIL |
Michael Zawacki
|
|
|
No stabalized entrance, dirt on road all the way until the end of Hudson.
|
General Inspection | 12/21/2018 | 12/21/2018 | 12/21/2018 | | FAIL |
Andy J. Long
|
|
|
Corrections needed before end of next week:
- install rock construciton entrance. Push old rock back, install new lining and fresh angular rock with as much length and width possible. - finish process of rock placement along Hudson for worker parking. - change out DI bags on Hudson. - sweeper needs to include Federal Way southeast bound (toward broadway) to clean up shoulder and gutter.
Verbal corrections to RP JC. Some changes have been made and Hudson scraped back, but there is a lot of mud on Hudson and alomst to Targee.
|
General Inspection | 11/5/2018 | 11/5/2018 | 11/9/2018 | | FAIL |
Michael Zawacki
|
|
|
Construction entrance is compacted, lots of dirt on road. Employees are parking on shoulder, all dirt, should be gravel to prevent mud when wet.
|
General Inspection | 9/18/2018 | 9/18/2018 | 9/18/2018 | | DEFR |
Michael Zawacki
|
|
|
See ESC17-01754 for project details
|