General Inspection | 3/19/2019 | 3/19/2019 | 3/19/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 3/4/2019 | 3/4/2019 | 3/4/2019 | | PART |
Michael Zawacki
|
|
|
Still not landscaped. Pile of landscape rock dumped on sidewalk and street.
|
General Inspection | 2/13/2019 | 2/13/2019 | 2/13/2019 | | PASS |
Michael Zawacki
|
|
|
Exterior completed, still needs landscaping. No runoff from site.
|
General Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | | PASS |
Michael Zawacki
|
|
|
Home exterior work completed, site still needs landscaping. No dirt running off from site.
|
General Inspection | 12/19/2018 | 12/19/2018 | 12/19/2018 | | PASS |
Michael Zawacki
|
|
|
Exterior work on home completed. Gator guard protecting sidewalk. Lot still needs landscaping.
|
General Inspection | 11/29/2018 | 11/29/2018 | 11/30/2018 | P | FAIL |
Andy J. Long
|
|
|
Clean up all loose trash. Sweep sidewalk and gutter.
|
General Inspection | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Michael Zawacki
|
|
|
Foundation completed, skid steer on site backfilling. Gator guard along perimeter. Sharing common access point with neighboring parcel.
|
General Inspection | 6/20/2018 | 6/20/2018 | 6/21/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on two adjacent Canyon Crest homes. 3rd lot being used for concrete washout, which is lined and away from sidewalk. Permit signs posted. No trackout.
Correction needed: - install wattle or silt fence below stockpile to prevent runoff to washout and street.
Notified RP-GC Dave
|
General Inspection | 6/13/2018 | 6/13/2018 | 6/13/2018 | P | PASS |
Michael Zawacki
|
|
|
Site excavated and foundation pouring has begun. Washout constructed and used. Backfill is mostly behind home site. No ESC issues.
|
Site Preparation | 6/6/2018 | 6/6/2018 | 6/6/2018 | P | PASS |
Michael Zawacki
|
|
|
Dave Phone #: ###-#### Met with contractors on site. Will use gatorguard along perimeters and clean as needed. Have permission to store backfill in neighboring lot, may haul off site if needed. Were made aware neighbors are monitoring site.
|
Site Preparation | 6/6/2018 | 6/6/2018 | 6/6/2018 | A | CANC |
Michael Zawacki
|
|
|
|