Site Final | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on interior. Lot is landscaped and stable.
|
Aging Inspection | 5/18/2020 | 5/18/2020 | 5/18/2020 | | CANC |
Andy J. Long
|
|
|
|
Aging Inspection | 3/16/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Michael Zawacki
|
|
|
Exterior work completed and lot landscaped.
|
Aging Inspection | 1/13/2020 | 1/13/2020 | 1/14/2020 | | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 11/11/2019 | 11/11/2019 | 11/12/2019 | | PASS |
Michael Zawacki
|
|
|
WIP on 2 homes at parcel. Site contained.
|
Aging Inspection | 9/9/2019 | 9/9/2019 | 9/9/2019 | | PASS |
Michael Zawacki
|
|
|
Contained, no esc issues.
|
Site Final | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | NR |
Andy J. Long
|
|
|
Work still in progress. No violations.
|
Aging Inspection | 6/4/2019 | 6/4/2019 | 6/4/2019 | | PASS |
Michael Zawacki
|
|
|
Exterior completed, site surrounded by maintained lawn.
|
Aging Inspection | 4/3/2019 | 4/3/2019 | 4/3/2019 | | PASS |
Michael Zawacki
|
|
|
Addition all framed, driveway poured. Most of lot is covered again with grass, some exposed area by alley. No ESC issues.
|
Aging Inspection | 1/31/2019 | 1/31/2019 | 1/31/2019 | | PASS |
Michael Zawacki
|
|
|
Addition framed, driveway completed, no washout on site. Material is stored on driveway, very little ground disturbance.
|