Permit Information
Permit NumberESC18-00616
StatusFinaled
Name BRIAN TERRY
Site Address 8000 S FEDERAL WAY
Project NameC29427 Micron Site Nitrogen
Customer Number 
ePlanReviewNo
Description
The project site is approximately 2 acres and consists of construction of a new Nitrogen manufacturing facility with associated infrastructure.
The Project includes underground utility work including water, power, gas, and storm
sewer lines construction and relocation. Structural fill work, concrete foundation work,
walkway and roadway construction with aggregate base, site landscaping, and stormwater
ditch construction is also anticipated as part of the project.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled8/22/20198/22/20198/22/2019PPASS
DetailsAndy J. Long
Grading complete, see ESC18-00251
General Inspection7/24/20198/6/20198/7/2019APASS
DetailsAndy J. Long
9 AM Micron Campus inspection

- updated SWPPP binders and site maps; weekly site inspections; permit info posted
- designated construction access route and track-out control
- storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron.
- large capacity lined concrete washout containment pit
- covered trash dumpsters/material separation
- containers for material and equipment storage prevent exposure to rain
- spill kits located in various locations around site.
- water trucks on duty to keep down dust.

No violations observed. Site is clean, BMPs are installed correctly, SWPPP record keeping is satisfactory. No correction requests at this time, Micron projects are currently in compliance.
General Inspection6/18/20196/18/20196/19/2019 CANC
DetailsAndy J. Long
General Inspection4/30/20194/30/20194/30/2019 CANC
DetailsAndy J. Long
to be inspected with fab 51 final
General Inspection3/14/20193/14/20193/15/2019 CANC
DetailsAndy J. Long
General Inspection10/2/201810/4/201810/4/2018APASS
DetailsAndy J. Long
9 AM wth Brian Terry and Susan Beesley, Micron environmental compliance division. Inspection conducted by ESC Inspectors Long and Zawacki

Micron SWPPP inspection of all construction projects with earth disturbance and use of staging and laydown areas. The CUP, Nitrogen plant, and B37 are under construction. B37 parking lots should be paved before end of month. Interior work is still occuring on Fab 51. Pathway is in progress around perimeter of site. Parking lot expansion at the MASK building on Columbia.

SWPPP inspections are conducted weekly by Micron stormwater team as well as contractors (Air Products, ESI, Stock, Warner) . SWPPP binders, site maps, and inspection reports were available for review and are well organized and complete.

Light rain and wind at time of inspection.

BMPs installed:
- construction trackout control with rock and rumble bars for both access points (B37 and laydown/employee parking)
- parking and laydown area access route has certain areas with rock and geotextile berms to prevent runoff from leaving the construction area into Micron employee parking.
- storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron.
- lined concrete washouts
- large covered dumpsters
- containers for material and equipment storage prevent exposure to rain
- spill kits located in various locations around site.
- water trucks onsite to keep down dust.

No violations observed. Site is clean, BMPs are installed correctly, site is inpsected regularly. No correction requests at this time, Micron projects are currently in compliance.