Site Final | 9/19/2018 | 9/20/2018 | 9/20/2018 | A | PASS |
Andy J. Long
|
|
|
11 AM west airport gate
Stormwater pond enlargement project is complete. Pond slopes have been stabililzed with rock, vegetation is not desired to prevent attracting wildlife. DI bags on airport access road to be removed this afternoon. Airport facility management will be placing rock on the tracked north facing slopes. Wattle can remain per airport decision. Recommend removing stakes and leaving wattle in place.
ESC permit conditions satisfied.
|
General Inspection | 8/21/2018 | 9/7/2018 | 9/7/2018 | A | PASS |
Andy J. Long
|
|
|
Stormwater pond has been widened, graded sides have been horizontally tracked. No work at time of inspection. Perimeter controls installed. Approved.
|
Site Preparation | 8/14/2018 | 8/21/2018 | 8/21/2018 | A | PASS |
Andy J. Long
|
|
|
Shane ###-####
ESC permit sign project located at the west end security gate parking area off Orchard (under flight light bridge). Stormwater pond is being enlarged and north fencing relocated.
Project area BMPs include: - perimeter sediment control wattle properly installed on north side of project. - Water truck onsite to control fugitive dust during excavation. - airport access road storm drains have sediment filter bags installed. - RP on duty for weekly inspections.
|