General Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 7/29/2019 | 7/29/2019 | 7/29/2019 | | PASS |
Michael Zawacki
|
|
|
Landscaped and stable, will final when BLD is closed.
|
General Inspection | 7/12/2019 | 7/12/2019 | 7/15/2019 | | PASS |
Michael Zawacki
|
|
|
Landscaped crew on site, no trackout.
|
General Inspection | 6/27/2019 | 6/27/2019 | 6/27/2019 | | PASS |
Michael Zawacki
|
|
|
Front yard still needs to be landscaped. Sewer work was in front of house.
|
General Inspection | 6/11/2019 | 6/11/2019 | 6/11/2019 | | PASS |
Michael Zawacki
|
|
|
Backyard is landscaped. Work on driveway out front. Crestline sewer work is currently in front of home.
|
General Inspection | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Michael Zawacki
|
|
|
Franz Whitte on site landscaping. No runoff down hill or rills.
|
Site Preparation | 8/7/2018 | 8/8/2018 | 8/8/2018 | A | PASS |
Michael Zawacki
|
|
|
Updated RP to be Ren Nelson who is also site manager. Silt fence is along rear, property line extends further down hill. Site is cleaned up during day. Storage will be in rear, plan on unloading in driveway and using skid steer to bring around, avoid any extra vehicles on dirt. Will use outpak when doing concrete work. Some irragation water runs onto street, will put sand bags in gutter to collect sediment.
|
Site Preparation | 8/7/2018 | 8/8/2018 | 8/8/2018 | P | CANC |
Andy J. Long
|
|
|
Dusty Phone #: ###-####
duplicate inspection request
|