Permit Information
Permit NumberESC18-01651
StatusFinaled
Name JOEL HIRTLE
Site Address 6008 S CHINOOK WAY
Project Name2-5 Fork South
Customer Number 
ePlanReviewNo
Description
per attached conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/31/201911/19/201911/20/2019PPASS
DetailsMichael Zawacki
DOC - Permit Finaled11/6/201911/6/201911/6/2019PPASS
DetailsMichael Zawacki
Aging Inspection10/31/201910/31/201910/31/2019 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection1/17/20191/17/20191/17/2019PPASS
DetailsMichael Zawacki
WIP, the cleanest lot in development.
General Inspection1/4/20191/10/20191/10/2019PPASS
DetailsAndy J. Long
follow up on corrections
- concrete washout rock entrance
- wattles on house with slope on corner
- clean out full DIs


Corrections complete. New rock at washout, DI bags maintained/emptied. House down the way had sediment control wattle installed.
General Inspection12/28/20181/2/20191/4/2019PFAIL
DetailsAndy J. Long
corrections not complete. No new violations.

2nd request to RP Joel to complete corrections by Thursday 1/10 PM
General Inspection12/19/201812/26/201812/28/2018APEND
DetailsAndy J. Long
BMP Violation12/18/201812/18/201812/19/2018PPART
DetailsAndy J. Long
re-inspection. fees must be paid first

New lined and marked construction washout pit installed. Fees paid.

Corrections still remaining:
-install rock access at washout to prevent trackout and spillage

- DI bag maintenance and street sweeping at Chinook and Old Country
- DI bag maintenance at end of Sturgeon, north of Spur
- sweep all dirty sites
- pick up trash along north fence line and open space next to community paty

Corrections requested to Joel.

Follow up next week scheduled.
BMP Violation12/17/201812/17/201812/17/2018PFAIL
DetailsAndy J. Long
Corrections needed:

- post permit signs on active projects
- do maintenance on DI bags along Chinook.
- no concrete washout; washout dumped in various locations around site.

Wrong RP listed on permit.


Correction given to CBH Colby. He stated RP for South Fork is Joel Hirtle.

Special investigation fee, parcel hold, and reinspection fee assessed. Reinspection required to check for new washout.