General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/31/2020 | 2/4/2020 | 2/4/2020 | P | PASS |
Andy J. Long
|
|
|
Project near complete. Perimeter is landscaped and site fully paved. No ESC violations observed. Will do site final walk next inspection
|
General Inspection | 1/30/2020 | 1/30/2020 | 1/31/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 12/30/2019 | 12/30/2019 | 12/30/2019 | | PASS |
Michael Zawacki
|
|
|
Building shell completed and lot paved. Landscaping has begun. Site is clean and trash free, no esc issues.
|
General Inspection | 11/28/2019 | 11/28/2019 | 11/29/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/28/2019 | 10/28/2019 | 10/28/2019 | P | PASS |
Michael Zawacki
|
|
|
All paved, only exposed area is on west near fivemile where thewy have started on gas station building. Foundation poured, no perimeter control, water should flow into site but will monitor. Dumpster and metal bin on site, no issues.
|
General Inspection | 10/1/2019 | 10/1/2019 | 10/1/2019 | | PART |
Michael Zawacki
|
|
|
Met with foreman on site. Currently hauling in good base material and hauling out old material. Some trackout into parking lot, will sweep when done. Plans on being paved in 2 weeks. Concrete crews using washout, entire site is still below grade.
|
General Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Michael Zawacki
|
|
|
Site is contained to corner, cut out of parking lot and below surrounding grade. No dust from current work, stockpile on site. Some tracking into parking lot, RP knows to sweep. Eco pan on site.
|
General Inspection | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | PASS |
Michael Zawacki
|
|
|
Site stripped, seepage pit awaiting inspection. Only concerns currently are blown dust and trackout. Gave foreman green sign,filled out and in window.
|
Site Preparation | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Michael Zawacki
|
|
|
Work began without site prep. Current work is stripping of old pavement only. No perimeter or dust controls on site, will be needed before excavation begins.
|