Site Final | 7/27/2020 | 7/29/2020 | 7/29/2020 | P | NR |
Michael Zawacki
|
|
|
Still working on demo of old school.
|
General Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 6/25/2020 | 6/25/2020 | 6/29/2020 | | PASS |
Michael Zawacki
|
|
|
New school is completed. Franz Whitte doing landscaping. WIP on demo of old school.
|
General Inspection | 5/25/2020 | 5/25/2020 | 5/27/2020 | | PASS |
Michael Zawacki
|
|
|
New school is about done. Still has some landscaping. Demo on old school begun. Crews are stripping and doing abatement work. Trees have fences at drip lines. No issues at time of inspection.
|
General Inspection | 4/23/2020 | 4/23/2020 | 4/23/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/23/2020 | 3/23/2020 | 3/24/2020 | | PASS |
Michael Zawacki
|
|
|
Franz Whitte on site installing irragation system. Curb and gutters completed, paving has begun.
|
General Inspection | 2/11/2020 | 2/20/2020 | 2/20/2020 | P | PART |
Michael Zawacki
|
|
|
Track out down Kingston. Talked to superintendant. They close the gate at 3 and sweep everything back to site. Lurre is hauling in fill. Most work is interior. School district wants to be moved in for when classes resume after spring break. Old school will be demoed when move over completed, Ideal is contractor.
|
General Inspection | 2/10/2020 | 2/10/2020 | 2/11/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 1/9/2020 | 1/9/2020 | 1/10/2020 | | PART |
Michael Zawacki
|
|
|
All current work is interior. Site will need a new washout before any more concrete pours. Lots of frozen dirt tracked onto road, looks like it was swept and froze in a film on surface.
|
General Inspection | 12/9/2019 | 12/9/2019 | 12/9/2019 | | PASS |
Michael Zawacki
|
|
|
Entire work area is below surrounding grade. New rock has been added to entrance. Exterior work nearly completed. Building area is surrounded by sand, is currently frozen, there is a few puddles in area, people parked in sanded area. Site is tras hfree. No trackout from site.
|
General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 | | PASS |
Michael Zawacki
|
|
|
Access from Kingston, no trackout, entrance built. Material being stored in old parking lot at entrance. Large washout on sites. Entire area surronded by pit run. Walls and roof on, lots of interior work. Workers installing seepage bed behind school.
|
General Inspection | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with foreman on site. Concrete washout is full, will be removed. Some small trash on site, has masons going around cleaning up. Site has ring of pitrun that should keep from becoming muddy. Still has Lurre's sweeper on site. Will have Lurre extend entrance when back on site.
|
Site Preparation | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | PASS |
Michael Zawacki
|
|
|
Talked with Matt with Lurre and gave him OK to start dirtwork to install entrance, Lurre also owns their own sweeper. Syman is doing SWPPP, will get board delivered. Access for phase 1 will be of Kingston Dr. Wattle along houses on norther perimeter, will keep vegetative buffer in place. Will bring water truck when site gets dusty.
|