Information based on query as of Wednesday, July 3, 2024.
Permit Information
Permit NumberESC19-00116
StatusIssued
Name TROY LAMKEY
Site Address 3500 N CABARTON LN
Project NameMountain View Elementary
Customer Number 
ePlanReviewNo
Description
Provide new 47,00 s.f. elementary school on same site as existing school. Upon completion of the new school the old school shall be demolished.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final7/27/20207/29/20207/29/2020PNR
DetailsMichael Zawacki
Still working on demo of old school.
General Inspection7/27/20207/27/20207/27/2020 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection6/25/20206/25/20206/29/2020 PASS
DetailsMichael Zawacki
New school is completed. Franz Whitte doing landscaping.
WIP on demo of old school.
General Inspection5/25/20205/25/20205/27/2020 PASS
DetailsMichael Zawacki
New school is about done. Still has some landscaping.
Demo on old school begun. Crews are stripping and doing abatement work. Trees have fences at drip lines. No issues at time of inspection.
General Inspection4/23/20204/23/20204/23/2020 CANC
DetailsAndy J. Long
General Inspection3/23/20203/23/20203/24/2020 PASS
DetailsMichael Zawacki
Franz Whitte on site installing irragation system. Curb and gutters completed, paving has begun.
General Inspection2/11/20202/20/20202/20/2020PPART
DetailsMichael Zawacki
Track out down Kingston. Talked to superintendant. They close the gate at 3 and sweep everything back to site.
Lurre is hauling in fill. Most work is interior. School district wants to be moved in for when classes resume after spring break. Old school will be demoed when move over completed, Ideal is contractor.
General Inspection2/10/20202/10/20202/11/2020 CANC
DetailsAndy J. Long
rescheduled
General Inspection1/9/20201/9/20201/10/2020 PART
DetailsMichael Zawacki
All current work is interior.
Site will need a new washout before any more concrete pours.
Lots of frozen dirt tracked onto road, looks like it was swept and froze in a film on surface.
General Inspection12/9/201912/9/201912/9/2019 PASS
DetailsMichael Zawacki
Entire work area is below surrounding grade.
New rock has been added to entrance.
Exterior work nearly completed. Building area is surrounded by sand, is currently frozen, there is a few puddles in area, people parked in sanded area.
Site is tras hfree.
No trackout from site.
General Inspection11/7/201911/7/201911/7/2019 PASS
DetailsMichael Zawacki
Access from Kingston, no trackout, entrance built. Material being stored in old parking lot at entrance. Large washout on sites. Entire area surronded by pit run. Walls and roof on, lots of interior work. Workers installing seepage bed behind school.
General Inspection10/1/201910/1/201910/1/2019PPASS
DetailsMichael Zawacki
Met with foreman on site.
Concrete washout is full, will be removed.
Some small trash on site, has masons going around cleaning up.
Site has ring of pitrun that should keep from becoming muddy. Still has Lurre's sweeper on site.
Will have Lurre extend entrance when back on site.
Site Preparation4/15/20194/16/20194/16/2019APASS
DetailsMichael Zawacki
Talked with Matt with Lurre and gave him OK to start dirtwork to install entrance, Lurre also owns their own sweeper.
Syman is doing SWPPP, will get board delivered.
Access for phase 1 will be of Kingston Dr.
Wattle along houses on norther perimeter, will keep vegetative buffer in place.
Will bring water truck when site gets dusty.