Site Final | 4/23/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Michael Zawacki
|
|
|
check that DI bag on Eagleson south of common drive is removed.
|
Site Final | 4/23/2020 | 4/23/2020 | 4/23/2020 | P | NR |
Andy J. Long
|
|
|
Near completion. Yard is landscaped. Notified RP to remove DI bag installed on Eagleson south of site.
|
General Inspection | 4/3/2020 | 4/6/2020 | 4/6/2020 | P | PASS |
Michael Zawacki
|
|
|
Working on interior. Outside completed and lot landscaped.
|
Aging Inspection | 4/3/2020 | 4/3/2020 | 4/3/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Michael Zawacki
|
|
|
Pad is poured and framing for subfloor has begun. All of the footprint is currently covered with poly. ackfill has been replaced, common drive is clean.
|