Permit Information
Permit NumberESC19-00601
StatusFinaled
Name LEVI JONES
Site Address 470 W PASO FINO DR
Project NameBIBENS-DIRX RESIDENCE
Customer Number 
ePlanReviewNo
Description
per ESC conditions. Site preparation inspection is REQUIRED. Plan calls for stabilized rock construction entrance off Paddock and down gradient wattle along Paso Fino and corner of Paddock. Receiving storm drains must have sediment protection installed and removed at end of project.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final3/20/20203/23/20203/24/2020PPASS
DetailsAndy J. Long
Home complete and occupied. Grass is starting to grown. Temporary BMPs have been removed. No ESC requests, ESC permit finaled.
General Inspection3/20/20203/20/20203/20/2020 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection3/3/20203/3/20203/4/2020 PASS
DetailsMichael Zawacki
Lot hydroseeded, no growth.
General Inspection2/13/20202/13/20202/14/2020 CANC
DetailsAndy J. Long
General Inspection1/27/20201/27/20201/27/2020PPASS
DetailsMichael Zawacki
No issues with tackifier, no runoff from site.
General Inspection12/23/201912/23/201912/23/2019PPASS
DetailsMichael Zawacki
Home is finished and lot has been tackified. No growth yet.
General Inspection11/19/201911/27/201911/27/2019PPASS
DetailsMichael Zawacki
Home completed. Lot has been hydroseeded. DI protection still installed.
General Inspection11/19/201911/19/201911/19/2019PPASS
DetailsAndy J. Long
?WIP on installing irrigation lines. Roof top gutters are connected to subdivision stub ins. Will follow up for sweep of loose dirt from the irrigation lines.
General Inspection10/14/201910/15/201910/14/2019APASS
DetailsMichael Zawacki
Home is framed and roofed, no gutters. Perimeter protected by wattle and silt fence. Some trash around site, none has blown away.
General Inspection8/15/20198/21/20198/21/2019PFAIL
DetailsMichael Zawacki
Construction entrance not installed as requested.
Apron mostly swept, some dirt on one side. Large pile of trash in front of garage door, risk of plastic and boxes blowing away, trash box also on site.
BMP Violation8/12/20198/12/20198/15/2019PPART
DetailsAndy J. Long
follow up on concrete washout dump.

Concrete washout dumped on Corralero has been cleaned up as requested.

Perimter BMPs installed, no trackout, site is clean.

Correction needed:
- install stabilized construction entrance
BMP Violation8/2/20198/5/20198/12/2019PPEND
DetailsAndy J. Long
concrete washout dumped across street in vacant lot

RP-GC has agreed to clean up. Jones Homes is on warning
General Inspection6/20/20197/8/20197/8/2019PPASS
DetailsMichael Zawacki
Foundation has been poured, looks like washout was hauled away. Site is clean and contained, no activity at time of inspection.
Site Preparation6/19/20196/20/20196/20/2019APASS
DetailsAndy J. Long
Wes Phone #: ###-####

Permit sign posted. Perimeter sediment contrlos (wattles and silt fence) installed properly. RP on site. Storm drains have sediment protection. RP states that he will have pump truck service take care of the washout instead of having onsite washout.

Excavation to begin next week. Approved for construction.