Site Final | 1/17/2020 | 1/17/2020 | 1/21/2020 | P | PASS |
Michael Zawacki
|
|
|
Grading final requested, GRD19-00049. Info sent to Jason Taylor.
|
Tracking Control | 12/16/2019 | 12/18/2019 | 12/20/2019 | P | PASS |
Andy J. Long
|
|
|
Construction entrance extended and more rock placed. Still some trackout. Need to clean up clods out of road.
|
General Inspection | 12/13/2019 | 12/13/2019 | 12/16/2019 | P | FAIL |
Andy J. Long
|
|
|
Construction entrance is small gravel rock, not larger angular rock. Entrance needs to be extended. Recommend over 75 feet. Very muddy conditions on cut road into site. Should consider putting road mix down and designate parking areas out of mud.
|
General Inspection | 11/1/2019 | 11/1/2019 | 11/6/2019 | P | PASS |
Michael Zawacki
|
|
|
Realigning creek started from north working sw through site. New channel is defined, more in the northern section of site. Some rock armoring has been installed on curves. Evidence of sprayed water for compaction. Strip of land grubbed parrallel to creek, most of site still has natural cover. No esc issues, work area is isolated.
|
Site Preparation | 10/15/2019 | 10/15/2019 | 10/16/2019 | P | PASS |
Michael Zawacki
|
|
|
ork has begun on creek channel. Entrance is on south of old Fred Meyer distro. Gravel entrance, work is a few hundred yards back. Lots of vegetation on site. Will not need to haul away striped material. Water truck on site, needs to cross Gowen to fill.
|