INSP-Final Inspection | 9/12/2001 | 9/12/2001 | 9/12/2001 | P | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 9/12/2001 4:25:42 PM
|
INSP-Final Inspection | 8/8/2001 | 8/8/2001 | 8/8/2001 | A | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 8/8/2001 10:55:13 AM
|
INSP-Final Inspection | 3/27/2000 | 3/28/2000 | 3/28/2000 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/27/2000 at 17:09:36. Contact: . Final ok for temp. occ. need gate hardware 3/29/00 10:11:22 AM
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2000 | 3/28/2000 | 3/28/2000 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/27/2000 at 17:08:36. Contact: . Ok on hydro test of fire dept. correction. 3/28/00 1:37:25 PM
|
INSP-Final Inspection | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | FAIL |
Joe Tawney
|
|
|
mike ###-#### Final not ready for inspe. 3/27/00 10:06:34 AM
|
INSP-Supply line flush | 3/9/2000 | 3/9/2000 | 3/9/2000 | P | PART |
Joe Tawney
|
|
|
mike ###-#### Ok on underground flush. 3/14/00 11:03:01 AM
|
INSP-Sprinkler Rough-in | 2/22/2000 | 2/23/2000 | 2/23/2000 | A | PART |
Joe Tawney
|
|
|
###-#### Ok on partial R/I ok to cover. 2/24/00 10:57:59 AM
|