Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR00-00123
StatusFinaled
Name GRINNELL FIRE PROTECTION
Site Address 205 N 10TH ST
Project NameSPR US BANK BUILDING ATTIC
Customer Number 
ePlanReview 
Description
US Bank portion of the Empire Building fire sprinklers. To install a new dry pipe fire sprinkler system for the US Bank attic. Modify riser and upgrade and add fire sprinklers on the wet system. All work to be per NFPA 13-1996 as adopted by the State Fire Marshal. BLD99-02856 *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/11/20023/14/20023/14/2002APASS
DetailsRick Jackson
fire fn todd- ###-#### completed on 3/13/02 3/14/2002 9:28:55 AM
INSP-Final Inspection3/13/20023/13/20023/13/2002APASS
DetailsRick Jackson
Added by Inspector: 409 On 3/13/2002 8:45:47 AM
INSP-Final Inspection2/4/20022/11/20022/11/2002AFAIL
DetailsRick Jackson
###-#### need accessible inspectors test currently located on roof; access is through a window. Need blue tag on riser 2/11/2002 3:54:47 PM
INSP-Final Inspection1/30/20022/4/20022/4/2002ACANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/30/2002 at 09:53:00. Contact: ###-####.
INSP-Sprinkler Rough-in/Hydro3/14/20013/14/20013/14/2001PPART
DetailsRick Jackson
Added by Inspector: 409 On 3/14/2001 2:56:37 PM hydro complee for wet and dry systems
INSP-Sprinkler Rough-in/Hydro11/15/200011/16/200011/16/2000PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/15/2000 at 15:21:25. Contact: ###-####.////// this inspection not ready 11/16/2000 3:58:59 PM