Permit Information
Permit NumberFIR00-00200
StatusFinaled
Name TREASURE VALLEY FIRE
Site Address 300 N STEELHEAD WAY
Project NameSPR UPGRADE STEELHEAD
Customer Number 
ePlanReview 
Description
STEELHEAD WAY WAREHOUSE/S. TO UPGRADE THE FIRE SPRINKLER SYSTEM TO MEET THE USE AND ANTICIPATED WAREHOUSING USE OF THIS ENTIRE FACILITY. SPRINKLER SYSTEM IS DESIGNED FOR GROUP IV NON-ENCAPSILATED COMMODITIES, RACK STORAGE (SINGLE/DOUBLE ROW) OPEN OR OPEN PALLET SUPPORT, (NO SOLID SHELVING ALLOWED) @ 22'-0" ELEVATION WITH MINIMUM 4'-0" AISLE WIDTH. INCLUDES NEW OR RELOCATED HOSE STATIONS, NEW 1,500 GPM FIRE PUMP, JOCKEY PUMP, CONTROL PANELS FOR EACH, PUMP TEST HEADER AND ALL RELATED FIRE PROTECTION WORK. INSTALLATION SHALL CONFORM TO NFPA 231C, 1998 EDITION. EXISTING SPRINKLERED (NON HIGH PILED STORAGE) AREAS SHALL CONFORM TO NFPA 13, 1996. (THIS WORK IS A REQUIREMENT FOR EXISTING USE AND FUTURE OCCUPANCY PERMITTING) *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/9/200011/14/200011/14/2000APART
DetailsJoe Tawney
###-#### Alarm test Ok exc outside bell and Fire pump test report 11/14/2000 12:28:28 PM
INSP-Sprinkler Rough-in/Hydro8/8/20008/9/20008/9/2000APART
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 08/08/2000 at 13:27:11. Contact: ###-####. Ok above ground hydro test ok sprinkler R/I except check hose station location. 8/10/00 11:22:53 AM
INSP-Sprinkler Rough-in/Hydro8/4/20008/8/20008/8/2000APART
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 08/04/2000 at 11:31:25. Contact: ###-####. Witnessed booster pump test waiting for copy of test curve & report 8/8/00 2:17:41 PM