INSP-Final Inspection | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 3/2/2001 3:52:28 PM
|
INSP-Sprinkler Rough-in | 2/23/2001 | 2/27/2001 | 2/27/2001 | A | PART |
Rick Jackson
|
|
|
9 am ###-#### fire pump test with reps from BC, CM, TVFP and UW. The suction pressure remained positive and all indications from pressure readings are the pump passed and will meet the system demand. 2/27/2001 10:44:14 AM
|
INSP-Supply line flush | 2/22/2001 | 2/22/2001 | 2/22/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/22/2001 10:03:13 AM underground flush okay after repair to leak
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2001 | 2/20/2001 | 2/20/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 2/20/2001 3:31:55 PM underground hydro okay; repaired leak
|
INSP-Final Inspection | 2/5/2001 | 2/6/2001 | 2/6/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/05/2001 at 12:37:37. Contact: ###-####. pump suction at negative during 150% flow test. UW at test also. 4000gpms available at 20 psi. above 4000 gpms the pump has negative suction 2/7/2001 9:26:44 AM
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2001 | 2/1/2001 | 2/1/2001 | P | PART |
Rick Jackson
|
|
|
###-#### hydro on all systems 2/1/2001 4:13:11 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2001 | 1/31/2001 | 1/31/2001 | A | NR |
Rick Jackson
|
|
|
Sam ###-#### calle dnad they will reschedule 1/31/2001 10:54:51 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/3/2001 | 1/5/2001 | 1/5/2001 | A | PART |
Rick Jackson
|
|
|
Sam ###-#### hydro okay on parts 1/5/2001 10:43:24 AM
|
INSP-Supply line flush | 12/18/2000 | 12/20/2000 | 12/20/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/18/2000 at 13:42:09. Contact: .////// c/n issued as water supply won't meet demand - negative suction pressure on fire pumps 12/20/2000 3:20:40 PM
|
INSP-Sprinkler Rough-in | 12/13/2000 | 12/13/2000 | 12/13/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 12/13/2000 2:18:22 PM ///// tested foam system operation - tested okay - pass 12/13/2000 2:19:08 PM
|
INSP-Supply line flush | 12/6/2000 | 12/13/2000 | 12/13/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/06/2000 at 09:47:52. Contact: ###-####. not a flush - tested foam system operation 12/13/2000 2:19:48 PM
|
INSP-Sprinkler Rough-in | 12/12/2000 | 12/12/2000 | 12/12/2000 | P | FAIL |
Rick Jackson
|
|
|
###-####///// still getting negative pressure on suction for the pumps; 12/12/2000 3:31:46 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2000 | 12/11/2000 | 12/11/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 12/11/2000 4:15:37 PM /// attempted to test the fire pumps - pumps rated at 3000 gpms; at flow of 3750 gpms the residual pressure was -1psi. TVFP is trying to figure out what is wrong. 12/11/2000 4:17:11 PM
|
INSP-Supply line flush | 12/6/2000 | 12/11/2000 | 12/11/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/06/2000 at 09:46:19. Contact: ###-####. see r/i for this date 12/11/2000 4:17:43 PM
|
INSP-Sprinkler Rough-in | 11/3/2000 | 11/3/2000 | 11/3/2000 | P | PART |
Rick Jackson
|
|
|
sam- ###-#### r/i fire underground flush only - flush okay. 11/3/2000 3:37:57 PM
|
INSP-Sprinkler Rough-in | 5/19/2000 | 5/19/2000 | 5/19/2000 | P | PASS |
Rick Jackson
|
|
|
jim ###-#### r/i underground; okay to cover - 12 inch PVC main; coated per NFPA 24.
|