INSP-Final Inspection | 12/28/2001 | 12/28/2001 | 12/28/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 12/28/2001 9:48:52 AM
|
INSP-Sprinkler Rough-in | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | PART |
Rick Jackson
|
|
|
###-#### 4tha dn 5th floor heads in corridor complete 11/20/2001 7:15:19 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | PART |
Rick Jackson
|
|
|
###-#### RICK basement wet system hydro okay only 11/8/2001 8:28:21 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PART |
Rick Jackson
|
|
|
###-#### RICK basement dry system hydro okay 11/8/2001 7:55:26 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | PART |
Rick Jackson
|
|
|
###-#### RICK okay on hydro for stanpipe and pump areas only 11/5/2001 2:29:11 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2001 | 11/2/2001 | 11/2/2001 | P | CANC |
Rick Jackson
|
|
|
###-#### RICK wrong permit called in. 11/2/2001 1:53:50 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2001 | 10/30/2001 | 10/30/2001 | P | PART |
Rick Jackson
|
|
|
###-#### RICK hydro test on penthouse okay 10/30/2001 2:06:37 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/25/2001 | 10/25/2001 | 10/25/2001 | P | PART |
Rick Jackson
|
|
|
###-#### basement dry system hydro okay 10/25/2001 2:28:08 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/17/2001 | 10/17/2001 | 10/17/2001 | P | PART |
Rick Jackson
|
|
|
893-091 rick fifth floor hydro okay 10/17/2001 3:20:16 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2001 | 10/2/2001 | 10/2/2001 | P | PART |
Rick Jackson
|
|
|
###-#### rick 4th floor east side hydro okay 10/2/2001 3:33:17 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2001 | 9/27/2001 | 9/27/2001 | P | PART |
Rick Jackson
|
|
|
###-#### rick hydro okay on 3rd floor east 9/27/2001 3:06:24 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/24/2001 | 9/24/2001 | 9/24/2001 | P | PART |
Rick Jackson
|
|
|
###-#### rick 4th floor west hydro okay 9/24/2001 1:45:31 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Rick Jackson
|
|
|
rick ###-#### 3rd floor west system hydro okay; 2nd floor showers on west side okay to cover; sally port okay to cover 8/23/2001 11:44:47 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2001 | 8/17/2001 | 8/17/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/16/2001 at 12:16:29. Contact: ###-####. 2 floor hydro okay east side 8/17/2001 12:55:39 PM
|
INSP-Conference | 8/14/2001 | 8/15/2001 | 8/15/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/14/2001 at 10:22:05. Contact: ###-####. okay to cover hard lid areas on 3-4-5 floors in bathrooms, showers and courtroom vestibules 8/15/2001 8:54:13 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/1/2001 | 8/1/2001 | 8/1/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 07:51:55. Contact: ###-####. first floor hydro okay 8/1/2001 3:57:03 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/23/2001 | 7/24/2001 | 7/24/2001 | A | PASS |
Rick Jackson
|
|
|
Rick ###-#### hydro on 1st floor west system okay. requested plans for the retail spaces on first floor 7/24/2001 11:37:24 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2001 | 7/12/2001 | 7/12/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 7/12/2001 2:47:00 PM underground hydro okay
|
INSP-Supply line flush | 6/26/2001 | 6/27/2001 | 6/27/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/26/2001 at 13:02:05. Contact: ###-####. underground flush okay 6/27/2001 9:37:55 AM
|
INSP-Conference | 3/21/2001 | 3/22/2001 | 3/22/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/21/2001 at 11:52:33. Contact: ###-####. walked the entire building. systems not complete, corrrections needed for earthquaking hangers, ec. 3/22/2001 10:26:25 AM
|
INSP-Conference | 1/29/2001 | 1/29/2001 | 1/29/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 08:39:52. Contact: ###-####. r/i for penthouse only - okay 1/29/2001 3:40:48 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2001 | 1/11/2001 | 1/11/2001 | A | PART |
Rick Jackson
|
|
|
preliminary walk through of building with rick of TVFP. reviewed plans - city plans are in ricks plan desk in the building 1/11/2001 3:29:19 PM
|