INSP-Final Inspection | 7/9/2003 | 7/9/2003 | 7/9/2003 | P | PASS |
Troy Cobbley
|
|
|
please call before going ###-#### mick
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2003 | 6/23/2003 | 6/23/2003 | P | FAIL |
Troy Cobbley
|
|
|
KERRY- ###-#### Provide new friction loss for the different anti-freeze backflow preventer. Provide asbuilts with all changes. Signs for all valves and all other close out items as listed on the review notes. Provide verification that the new front canopies do not require protection since they appear to have combustibles inside. Pendants are still too close to supply registers. Provide clearance for operation of the PIV. Provide hydro test certificates 6/23/2003 2:08:21 PM
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2003 | 6/20/2003 | 6/20/2003 | P | CANC |
Troy Cobbley
|
|
|
contractor said the sprinkler piping has a leak so the hydro test could not be performed 6/20/2003 1:49:14 PM
|
INSP-Sprinkler Rough-in | 6/17/2003 | 6/18/2003 | 6/18/2003 | A | FAIL |
Troy Cobbley
|
|
|
kerry; Phone #: ###-#### Provide clamps on the FDC piping in the crawl space, remove tape from the sidewall heads in the second floor corridor, pendants are overspaced throughout the building. Sprinkler spacing is 149 sq. ft. max. Pendant sprinkler heads are less than one foot to supply registers thoughout the building as well 6/18/2003 11:50:26 AM
|
INSP-Sprinkler Rough-in | 6/26/2002 | 6/27/2002 | 6/27/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground flush OK 6/27/2002 10:26:48 AM
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2002 | 3/28/2002 | 3/28/2002 | A | PART |
Rick Jackson
|
|
|
###-#### TODD underground hydro only - okay 3/28/2002 10:45:19 AM
|
INSP-Sprinkler Rough-in | 2/21/2002 | 2/21/2002 | 2/21/2002 | A | PART |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/21/2002 10:24:43 AM Underground supply line from tap to 5' outside of building OK for cover. Inspection of PIV and ductile to be later
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2002 | 2/20/2002 | 2/20/2002 | P | NR |
Troy Cobbley
|
|
|
Inspection was to be for underground. Contractor cancelled because of trenching 2/20/2002 3:54:00 PM
|
INSP-Sprinkler Rough-in | 4/5/2001 | 4/6/2001 | 4/6/2001 | A | PART |
Joe Tawney
|
|
|
###-#### Spklr rough in. 2 Rooms overspaced. Add protection under stairs. Provide min 1 ft clearance from supply registers or install inter mediate temp heads. 4/6/2001 4:09:21 PM
|