INSP-Final Inspection | 8/13/2001 | 8/13/2001 | 8/13/2001 | A | PASS |
Joe Tawney
|
|
|
Added by Inspector: 406 On 8/13/2001 8:24:03 AM
|
INSP-Final Inspection | 11/6/2000 | 11/6/2000 | 11/6/2000 | P | FAIL |
Joe Tawney
|
|
|
fn insp- jim pager ###-#### Final Fail C/N issued 11/7/2000 7:05:10 AM
|
INSP-Final Inspection | 10/12/2000 | 10/12/2000 | 10/12/2000 | P | PART |
Joe Tawney
|
|
|
###-#### OK on rough in and hydro test of dry pipe system 10/13/2000 7:51:52 AM
|
INSP-Final Inspection | 10/6/2000 | 10/9/2000 | 10/9/2000 | A | PART |
Joe Tawney
|
|
|
Adam ###-#### OK on above ground hydro test of wet system 10/9/2000 11:38:27 AM
|
INSP-Sprinkler Rough-in | 10/4/2000 | 10/5/2000 | 10/5/2000 | A | PART |
Joe Tawney
|
|
|
UNDER GROUND ADAM ###-#### OK on underground Hydro test and supply line flush 10/5/2000 12:07:03 PM
|
INSP-Sprinkler Rough-in | 9/18/2000 | 9/18/2000 | 9/18/2000 | P | PART |
Joe Tawney
|
|
|
adam ###-#### -underground insp OK to cover supply line 9/18/2000 4:52:53 PM
|
INSP-Sprinkler Rough-in | 9/14/2000 | 9/14/2000 | 9/14/2000 | P | FAIL |
Joe Tawney
|
|
|
R/I --ADAM-- ###-#### Rough in Fail Overspacing in 2 areas 9/15/2000 7:47:47 AM
|