INSP-Final Inspection | 11/13/2001 | 11/10/2001 | 11/10/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/13/2001 7:20:03 AM completed
|
INSP-Supply line flush | 6/28/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/28/2001 3:20:22 PM north west riser only flush okay
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2001 | 6/6/2001 | 6/6/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 6/6/2001 5:33:31 AM thrust block installed; stub in complete for TVFP; still requires connection water main and flush 6/6/2001 9:44:29 AM
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2001 | 6/5/2001 | 6/5/2001 | P | FAIL |
Rick Jackson
|
|
|
underground hydro static test mark ###-#### pager 6/6/2001 5:32:56 AM thrust block not installed on east feed mains; will be ready on 6/6 6/6/2001 5:34:33 AM
|
INSP-Sprinkler Rough-in | 4/26/2001 | 4/27/2001 | 4/27/2001 | A | PART |
Rick Jackson
|
|
|
r/i --brad-- ###-#### for under ground hydro okay for K.1 and 34 grid lines underground 4/27/2001 10:50:52 AM
|