INSP-Sprinkler Rough-in/Hydro | 10/5/2001 | 10/5/2001 | 10/5/2001 | P | PASS |
Joe Tawney
|
|
|
Hydro test on FDC is OK. OK for perm occ. 10/5/2001 3:23:36 PM 10/5/2001 3:25:04 PM
|
INSP-Sprinkler Rough-in | 9/25/2001 | 9/25/2001 | 9/25/2001 | P | PART |
Joe Tawney
|
|
|
Added by Inspector: 406 On 9/25/2001 3:23:10 PM Spklr rough in 2 areas overspaced. Taped spklr heads, Heads too close to supply registers
|
INSP-Supply line flush | 9/19/2001 | 9/21/2001 | 9/21/2001 | A | PART |
Joe Tawney
|
|
|
OK on AG and UG hydro tests. FDC to be hydro tested when relocated. 9/20/2001 8:15:09 AM
|
INSP-Sprinkler Rough-in/Hydro | 9/14/2001 | 9/18/2001 | 9/18/2001 | A | FAIL |
Joe Tawney
|
|
|
Hydro test fail 9/18/2001 11:34:39 AM
|
INSP-Supply line flush | 9/14/2001 | 9/18/2001 | 9/18/2001 | A | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 09/14/2001 at 14:14:01. Contact: ###-####.
|
INSP-Supply line flush | 9/17/2001 | 9/17/2001 | 9/17/2001 | P | PART |
Joe Tawney
|
|
|
OK on underground flush 9/17/2001 3:33:47 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2001 | 8/27/2001 | 8/27/2001 | A | PART |
Joe Tawney
|
|
|
Spklr rough in Mains looked OK. There was discrepancy in plan review spacing and submitted calcs.on several remote areas 8/27/2001 12:59:21 PM
|
INSP-Conference | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | CANC |
Joe Tawney
|
|
|
PROFT Mtg. today @ 1:30
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2001 | 6/22/2001 | 6/22/2001 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 09:57:44. Contact: ###-####. stage area only okay to cover 6/22/2001 3:40:49 PM
|