Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR01-00106
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 897 N MAPLE GROVE RD
Project NameSPR LINGER LONGER BLD 6
Customer Number 
ePlanReview 
Description
BUILDING # 8 - TYPE A * TO FIRE SPRINKLER A NEW 22,292 FT/2, THREE STORY, WOOD FRAMED, 16 UNIT APARTMENT BUILDING. THE FIRST FLOOR IS 8,328 FT/2 AND CONTAINS 12 GARAGES, TWO, THREE TWO BEDROOM UNITS AND TWO ONE BEDROOM UNITS, THE SECOND FLOOR IS 8,514 FT/2 AND CONTAINS FOUR, TWO BEDROOM UNITS AND FOUR, ONE BEDROOM UNITS. THE THIRD FLOOR IS 5,550 FT/2 AND CONTAINS FOUR, TWO BEDROOM UNITS. ALL FIRE SPRINKLER WORK PER THE APPROVED PLANS, UFC, BCO AND RELATED, ADOPTED NFPA PAMPHLETS, AS REGULATED BY THE FIRE DEPARTMENT. NOTE: THIS BUILDING HAS A NFPA 13R FIRE SPRINKLER SYSTEM. BUILDING PERMIT IS: BLD00-02815. *JWA*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/27/20019/27/20019/27/2001PPASS
DetailsJoe Tawney
Added by Inspector: 406 On 9/27/2001 4:09:21 PM
INSP-Final Inspection9/24/20019/25/20019/25/2001APART
DetailsJoe Tawney
Ok on underground hydro test 9/25/2001 11:57:24 AM
INSP-Final Inspection9/20/20019/21/20019/21/2001AFAIL
DetailsJoe Tawney
Final Fail UG hydro test. Alarms tested OK.Need to finish walk thru 9/21/2001 12:20:58 PM
INSP-Sprinkler Rough-in/Hydro9/14/20019/17/20019/17/2001PCANC
DetailsJoe Tawney
Cancel To be rescheduled 9/17/2001 3:36:26 PM
INSP-Supply line flush9/12/20019/13/20019/13/2001APART
DetailsJoe Tawney
OK on supply line flush 9/13/2001 11:12:06 AM
INSP-Sprinkler Rough-in6/22/20016/22/20016/22/2001PPART
DetailsRick Jackson
###-#### r/i okay to cover; left tag in job shack; riser not complete 6/22/2001 3:41:42 PM