INSP-Final Inspection | 9/13/2001 | 9/13/2001 | 9/13/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/13/2001 at 08:14:24. Contact: ###-####.
|
INSP-Final Inspection | 9/11/2001 | 9/12/2001 | 9/12/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/11/2001 at 08:13:21. Contact: ###-####. water for services building sets off 3033 Elder building; should be priority 2 9/12/2001 2:47:31 PM
|
INSP-Final Inspection | 9/10/2001 | 9/11/2001 | 9/11/2001 | P | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/10/2001 at 11:07:27. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/11/2001 at 08:10:23.
|
INSP-Final Inspection | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail Monitoring station could not distinguish between supr and tbl signals 8/24/2001 6:16:03 PM
|
FIR-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | NR |
Rick Jackson
|
|
|
work in progress 8/6/2001 10:05:15 AM
|