INSP-Final Inspection | 11/13/2001 | 11/13/2001 | 11/13/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/13/2001 4:07:12 PM OK for perm occ
|
INSP-Final Inspection | 10/17/2001 | 10/19/2001 | 10/19/2001 | A | NR |
Troy Cobbley
|
|
|
This was not a final inspection. Shilo complete the items noted on the correction notice. Final to be scheduled later. 10/19/2001 1:47:20 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2001 | 10/8/2001 | 10/8/2001 | A | PASS |
Joe Tawney
|
|
|
Hydro test on underground and overhead system Ok
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2001 | 10/2/2001 | 10/2/2001 | P | PART |
Joe Tawney
|
|
|
Rough in OK but see correction notes. 10/2/2001 4:56:08 PM
|
INSP-Supply line flush | 9/24/2001 | 9/25/2001 | 9/25/2001 | A | PART |
Joe Tawney
|
|
|
OK on supply line flush 9/25/2001 11:47:18 AM
|
INSP-Supply line flush | 6/22/2001 | 6/22/2001 | 6/22/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/22/2001 at 10:03:51. Contact: ###-####.
|
INSP-Sprinkler Rough-in | 6/21/2001 | 6/21/2001 | 6/21/2001 | A | PART |
Joe Tawney
|
|
|
Added by Inspector: 406 On 6/21/2001 8:25:05 AM OK to cover spklr supply line
|
INSP-Supply line flush | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 14:09:44. Contact: ###-####. Ok to cover Riser stub in to bldg 5/18/2001 10:52:21 AM
|