INSP-Final Inspection | 11/5/2001 | 11/6/2001 | 11/6/2001 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler system finaled. OK for perm occ. 11/8/2001 11:43:45 AM
|
INSP-Final Inspection | 10/31/2001 | 11/2/2001 | 11/2/2001 | A | FAIL |
Troy Cobbley
|
|
|
Still have taped and painted heads, deli area pendents are too close, need calcs for 1" drops and letter for unsprinklered canopy
11/2/2001 12:04:20 PM
|
INSP-Final Inspection | 10/12/2001 | 10/15/2001 | 10/15/2001 | P | FAIL |
Troy Cobbley
|
|
|
See c/n. heads blocked at hvac's, combustible above meat/fish, painted/taped heads, pendants not on 1 1/4 drops in retail 10/15/2001 1:15:32 PM
|
INSP-Final Inspection | 10/2/2001 | 10/3/2001 | 10/3/2001 | P | CANC |
Joe Tawney
|
|
|
Cancelled by alarm contr. to be resch. later 10/3/2001 2:52:50 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2001 | 9/27/2001 | 9/27/2001 | P | PART |
Joe Tawney
|
|
|
OK on sprk. rough-in in garden area except two heads obs. and one strap to be bent. 9/27/2001 4:34:29 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2001 | 9/19/2001 | 9/19/2001 | P | PART |
Joe Tawney
|
|
|
Ok on FDC hydro test and OK on rough in of bldg materials area of dry system. Resubmittal required for garden area of dry system. 9/19/2001 3:52:30 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2001 | 9/18/2001 | 9/18/2001 | P | PART |
Joe Tawney
|
|
|
Ok on above ground hydro test of dry system. FDC piping still needs hydro test 9/18/2001 2:15:19 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/4/2001 | 9/5/2001 | 9/5/2001 | A | PART |
Joe Tawney
|
|
|
OK on above ground hydro test of system # 2. Still need hydro test of FDC 9/5/2001 2:52:02 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2001 | 8/28/2001 | 8/28/2001 | A | PART |
Joe Tawney
|
|
|
OK above ground hydro test on system # 4 8/27/2001 4:59:39 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | PART |
Joe Tawney
|
|
|
OK on rough in of food storage area. This completes rough ins for bldg. Ok on above ground hydro tests for systems 1 & 3. 8/24/2001 10:16:44 AM
|
INSP-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 8/14/2001 4:46:40 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/9/2001 | 8/10/2001 | 8/10/2001 | P | PART |
Joe Tawney
|
|
|
OK on rough of open sales area OK to cover areas on south side of store C/N issued for one room, duct and overhead door 8/10/2001 2:43:26 PM
|
INSP-Sprinkler Rough-in | 8/2/2001 | 8/3/2001 | 8/3/2001 | P | CANC |
Joe Tawney
|
|
|
###-#### Not ready 8/3/2001 2:40:04 PM
|
INSP-Sprinkler Rough-in | 8/2/2001 | 8/3/2001 | 8/3/2001 | P | CANC |
Joe Tawney
|
|
|
###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2001 | 7/19/2001 | 7/19/2001 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/17/2001 at 13:39:30. Contact: ###-####. kzy to cover ALE area; combustibles by Elements area to be covered 7/19/2001 10:37:17 AM
|