INSP-Final Inspection | 11/14/2001 | 11/14/2001 | 11/14/2001 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/14/2001 9:30:45 AM Fire sprinkler finaled. OK for perm occ
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2001 | 11/1/2001 | 11/1/2001 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 11/1/2001 2:49:14 PM above ground hydro test ok
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2001 | 10/31/2001 | 10/31/2001 | P | PART |
Troy Cobbley
|
|
|
add head north side riser room, install EQ bracing, heads overspace in southwest corner, northwest sprig ups to far from deck, need to see east concealed space 11/1/2001 2:47:26 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2001 | 10/4/2001 | 10/4/2001 | P | PART |
Joe Tawney
|
|
|
underground hydro test ok 10/5/2001 5:13:39 PM
|
INSP-Supply line flush | 10/3/2001 | 10/4/2001 | 10/4/2001 | P | PART |
Joe Tawney
|
|
|
supply line flush OK 10/5/2001 1:38:37 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/2/2001 | 10/4/2001 | 10/3/2001 | A | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/02/2001 at 16:48:59. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/03/2001 at 15:32:30.
|
INSP-Supply line flush | 10/2/2001 | 10/4/2001 | 10/3/2001 | A | CANC |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/02/2001 at 16:49:43. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/03/2001 at 15:33:21.
|
FIR-Aging Inspection | 9/18/2001 | 9/18/2001 | 9/18/2001 | | NR |
Joe Tawney
|
|
|
WIP 9/18/2001 2:16:17 PM
|