Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR01-00529
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1185 S VINNELL WAY
Project NameSPR GSA
Customer Number 
ePlanReview 
Description
GSA - BOISE CUSTOMER SERVICE CENTER * TO INSTALL A LIGHT HAZARD SYSTEM IN A NEW 30,755 FT/2, ONE STORY, OFFICE BUILDING, TEMPORARY HOLDING CELLS FOR IMMIGRATION PROCESSING, AND A OH-1 ANTIFREEZE SYSTEM IN A VEHICLE SALLYPORT. THIS BUILDING IS CONSTRUCTED OF CONCRETE SLAB FLOORS, MASONRY EXTERIOR WALLS, STEEL STRUCTURAL FRAME AND METAL ROOF DECK WITH SINGLE PLY ROOFING SYSTEM. THIS PERMIT INCLUDES APPROXIMATELY 126 FT OF 6" PVC C-900 FIRE SERVICE SUPPLY PIPING FROM THE PROPERTY LINE INTO A MECHANICAL / ELECTRICAL ROOM. ALL RELATED WORK SHALL BE PER THE UFC, RELATED AND ADOPTED NFPA PAMPHLETS, THE APPROVED PLANS AND ATTACHED REVIEW NOTES, AS REGULATED BY THE FIRE DEPARTMENT. THE FOUNDATION IS CONSTRUCTED AND COMPLETED UNDER BUILDING PERMIT BLD01-00620. THIS FIRE PERMIT IS ATTACHED TO BLD01-00621. (JWA)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/15/20022/15/20022/15/2002APASS
DetailsTroy Cobbley
Added by Inspector: 430 On 2/15/2002 8:29:05 AM fire sprinkler system finaled
FIR-Aging Inspection2/1/20022/1/20022/1/2002 NR
DetailsTroy Cobbley
work in progress 2/1/2002 11:58:30 AM
INSP-Sprinkler Rough-in/Hydro1/24/20021/25/20021/25/2002APASS
DetailsTroy Cobbley
above ground hydro test ok 1/25/2002 3:38:38 PM
INSP-Sprinkler Rough-in/Hydro12/28/200112/28/200112/28/2001PPASS
DetailsTroy Cobbley
hydro test for the antifreeze system OK 12/28/2001 3:20:07 PM