INSP-Final Inspection | 5/9/2003 | 5/9/2003 | 5/9/2003 | A | PASS |
Troy Cobbley
|
|
|
|
INSP-Final Inspection | 4/29/2002 | 5/2/2002 | 5/2/2002 | A | FAIL |
Troy Cobbley
|
|
|
Fire sprinkler riser devices have been tested along with one duct detector above the panel room. All other detectors and items in panel need to be tested 5/3/2002 8:25:22 AM
|
INSP-Final Inspection | 2/14/2002 | 2/19/2002 | 2/19/2002 | A | NR |
Troy Cobbley
|
|
|
Sprinkler system was not complete, fire alarm contractor did not have approved plans on site 2/19/2002 1:23:13 PM
|
INSP-Final Inspection | 2/13/2002 | 2/14/2002 | 2/14/2002 | A | CANC |
Troy Cobbley
|
|
|
canceled by contractor. He said it would be set up on Tuesday of next week 2/14/2002 1:50:28 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/29/2001 | 11/30/2001 | 11/30/2001 | A | PART |
Troy Cobbley
|
|
|
Cut back pipe in SE corner head to 7'-6" from draft stop, prove 1" pipe in SE corner, provide verification that hangers mounted to bottom chord is ok. Everything else can be covered. 11/30/2001 10:10:32 AM
|