Permit Information
Permit NumberFIR02-00272
StatusFinaled
Name IND SCHOOL DIST OF BOISE CITY
Site Address 1105 N 13TH ST
Project NameSPR NORTH JR. HIGH
Customer Number 
ePlanReview 
Description
(North Jr. High) To install fire sprinklers in a 11,772 ft/2 basement. Work includes installing a 6" C-900 PVC fire service supply from 13th Street main supply, west under the building footing. The main transitions from C-900 to "Ductile Iron" up into the crawl space then transitions again to schedule 10 steel, where it travels approximately 23'-0" through the crawl space into the basement. Also this fire sprinkler system is shown protecting several small janitor closets on the 1st floor and one storage area on the second floor. The fire sprinkler system work shall comply with NFPA 13?1999, attached review comment and conditions list; as regulated by the fire chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is not attached to any building permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/31/20031/31/20031/31/2003PPASS
DetailsRick Jackson
INSP-Sprinkler Rough-in/Hydro10/14/200210/14/200210/14/2002PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/14/2002 at 11:00:10. Contact: ###-####. underground hydro okay 10/14/2002 3:01:57 PM
INSP-Sprinkler Rough-in/Hydro9/26/20029/27/20029/27/2002PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/26/2002 at 15:49:20. Contact: ###-####. need EQ in locker room and on anti-freeze loop; head gaurds in southwest stair and in storage rooms; head overspaced in locker room; need anti-freeze in system; need alarm plans submitted for new tampers/flows; plans show ball drip in pit for FDC 9/27/2002 2:37:07 PM
INSP-Supply line flush9/20/20029/23/20029/23/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/20/2002 at 09:02:15. Contact: ###-####. underground flush okay; still need hydro on underground 9/23/2002 10:29:54 AM
INSP-Supply line flush9/16/20029/17/20029/17/2002ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/16/2002 at 12:25:08. Contact: ###-####. called Shilo office and they said no one was at the job site and they would recall an inspection 9/17/2002 4:07:11 PM
INSP-Sprinkler Rough-in9/13/20029/13/20029/13/2002PPART
DetailsRick Jackson
underground completed to basement wall; depth of bury will be 3 ft where it passes from exterior wall to basement wall; will need to flush and hydro
INSP-Supply line flush8/20/20028/20/20028/20/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 08/20/2002 at 08:04:58. Contact: ###-####. cover inspection for UG cover - okay to cover partial lay of new line; stubbed from street to within 10 feet of building; FDC is run in same trench and same distance from building 8/20/2002 10:17:53 AM
INSP-Conference8/19/20028/19/20028/19/2002PFAIL
DetailsRick Jackson
BUDDY ###-#### ( UNDERGROUND WATER SUPPLY ) need tracer wire, conduit for tamper on PIV ends of pipe capped 8/19/2002 4:14:37 PM