INSP-Final Inspection | 1/17/2012 | 1/18/2012 | 1/18/2012 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 1/4/2012 | 1/4/2012 | 1/4/2012 | | DEFR |
Troy Cobbley
|
|
|
|
FIR-Aging Inspection | 11/12/2010 | 11/12/2010 | 11/17/2010 | | NR |
Troy Cobbley
|
|
|
I spoke to Robert and he said he would follow up on project
|
FIR-Aging Inspection | 3/1/2010 | 3/1/2010 | 3/3/2010 | | DONE |
Troy Cobbley
|
|
|
Information forwarded to Scott Arellano for further action due to non responce of contractor.
|
FIR-Aging Inspection | 12/1/2005 | 12/1/2005 | 12/6/2005 | | NR |
Troy Cobbley
|
|
|
Phil will follow up.
|
INSP-Conference | 9/13/2005 | 9/23/2005 | 9/26/2005 | P | DONE |
Troy Cobbley
|
|
|
Jeff with Commercial Fire said he would get the inspectors test taken care of.
|
FIR-Aging Inspection | 9/13/2005 | 9/13/2005 | 9/13/2005 | | NR |
Troy Cobbley
|
|
|
I spoke to Ron Hagen with Sletten Companies about getting these permits finaled. He gave me the building owner, Allen Lindstrom, phone number where I left a message with a lady. She stated he would call me back today.
|
INSP-Conference | 6/16/2005 | 6/30/2005 | 6/30/2005 | P | NR |
Troy Cobbley
|
|
|
Phil left message that he would followup for final
|
INSP-Conference | 6/16/2005 | 6/16/2005 | 6/16/2005 | P | CANC |
Troy Cobbley
|
|
|
Followup for final
|
FIR-Aging Inspection | 6/16/2005 | 6/16/2005 | 6/16/2005 | | NR |
Troy Cobbley
|
|
|
I left message on Phil Omis's phone requesting the status of the job.
|
INSP-Final Inspection | 10/15/2002 | 10/16/2002 | 10/16/2002 | A | FAIL |
Troy Cobbley
|
|
|
no items on the correction list have been corrected. the contractor provided a new test orfice made of plastic hose which is not a listed item 10/16/2002 8:57:44 AM
|
INSP-Alarm Testing | 8/27/2002 | 8/27/2002 | 8/27/2002 | P | FAIL |
Troy Cobbley
|
|
|
provide Boise Fire Dept. approved knox box, change horn tone to temporal, provide sign on riser room door, verify correct orfice is being used for the sprinkler inspectors test 8/27/2002 2:41:49 PM
|