Permit Information
Permit NumberFIR02-00385
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 11193 W EMERALD ST
Project NameSPR Fresca Mexican Foods Ph-1
Customer Number 
ePlanReview 
Description
Fresca Mexican Foods - Phase 1 * To install a new 236'-0" of 8", C-900 PVC underground supply from the property line to a new 142 ft/2 Fire Pump House. To install 6", C-900 PVC underground supply from the Fire Pump House into an existing building (Room "C") for a new combination riser. To abandon the existing 6"underground supply feeding from Meadowland Drive and remove the existing remote FDC (new one to be located off the Fire Pump House). To connect the existing Double Interlock Pre-action system riser protecting the existing freezer onto the new riser supply (in Room "C"). To install a 1,500 gpm, 100 HP fire pump, controller, and pressure maintenance jockey pump, controller and related/required appurtenances and to install fire sprinkler protection throughout the entire facility. This project is Phase 1 of 3 phases; of which the final results will be to completely fire sprinkler the entire facility, meeting UBC requirements for area increase. (This building was originally constructed in Ada County and later annexed into Boise City). All fire sprinkler system installation work and equipment, materials and appurtenance shall comply with NFPA 13?1999, 24-1995, 20-1999, 72-1999, and attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and the fire Inspection Card are required to be on site as a condition of this work, to provide witness of compliance verification meeting minimum code. This permit is attached to building permit BLD02-01925.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/25/20034/25/20034/25/2003APASS
DetailsTroy Cobbley
Phase 1 fire sprinklers finaled.
INSP-Final Inspection4/22/20034/23/20034/23/2003PFAIL
DetailsTroy Cobbley
Remove batt insulation in attic space over the maint. shop, provide map for fire alarm system, upright sprinkler heads in the attic space over the maint. shop appear to be blocked by truss panels 4/23/2003 3:34:31 PM
INSP-Sprinkler Rough-in/Hydro4/22/20034/23/20034/23/2003PPASS
DetailsTroy Cobbley
need to complete air test; 40.5 psi and cooler at -22 degrees F. Air test is OK 4/23/2003 3:31:15 PM
INSP-Sprinkler Rough-in/Hydro4/22/20034/22/20034/22/2003PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 4/22/2003 at 6:42:45 AM. Contact: ###-####. stated 24 hr air test; 40.5 psi and freezer is at -22 degrees F. 4/22/2003 1:08:24 PM
INSP-Sprinkler Rough-in/Hydro3/27/20033/28/20033/28/2003PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 3/27/2003 at 5:19:52 PM. Contact: ###-####. forward flow of BFP okay; hydro on old wet system okay 3/28/2003 3:31:00 PM
INSP-Sprinkler Rough-in/Hydro3/19/20033/20/20033/20/2003APART
DetailsRick Jackson
RUSS; Phone #: ###-#### Internet Inspection Request from: Annette Moore hydro okay on all piping in pump room 3/20/2003 11:09:56 AM
INSP-Conference3/17/20033/19/20033/19/2003APASS
DetailsTroy Cobbley
above ground hydro test for the pre-action system in the freezer is ok. The system was tested from the control valve at base of riser 3/19/2003 2:25:11 PM
INSP-Sprinkler Rough-in3/17/20033/18/20033/18/2003AFAIL
DetailsTroy Cobbley
Inspection was for the 24 hour air test. Test was a fail due to freezer not being at the lowest nominal level. See NFPA 10-2.3.1 3/18/2003 3:59:33 PM
INSP-Conference3/11/20033/13/20033/13/2003PPART
DetailsTroy Cobbley
Inspection was for the testing of the fire pump. Russ with Nickerson pump was present to perform the test 3/13/2003 3:26:55 PM
INSP-Supply line flush3/7/20033/10/20033/10/2003PPASS
DetailsTroy Cobbley
underground hydro and flush ok 3/10/2003 3:40:18 PM
INSP-Supply line flush3/5/20033/7/20033/7/2003AFAIL
DetailsTroy Cobbley
The contractor is not getting enough flow for a flush due to 300' of hose. A minimum 880 gallons is required. Flush to be rescheduled 3/7/2003 11:21:48 AM
INSP-Conference12/23/200212/24/200212/24/2002ADONE
DetailsTroy Cobbley
spoke with the fire sprinkler and the general contractors about the pre-action fire sprinkler system 12/24/2002 10:02:19 AM
INSP-Conference12/20/200212/20/200212/20/2002PCANC
DetailsTroy Cobbley
cancelled by Jeff with Treasure Valley Fire 12/20/2002 3:42:45 PM
INSP-Conference12/11/200212/11/200212/11/2002PPART
DetailsTroy Cobbley
all underground is ok to cover except for the section that will tie to the united water stub-in 12/11/2002 3:51:27 PM
INSP-Conference12/10/200212/10/200212/10/2002PPART
DetailsTroy Cobbley
the remaining section of piping from the new riser to the pump room is OK to bury. 12/10/2002 4:08:19 PM
INSP-Conference12/9/200212/9/200212/9/2002PPART
DetailsTroy Cobbley
the inspection was from the north stub-in to the first 90 elbow and then three additional lenghts of pipe. This section of the underground I witnesses the bedding and the covering as well as the pipe being installed. It was OK to cover. The rest of the pipe will be inspected later 12/9/2002 4:24:20 PM