INSP-Final Inspection | 7/2/2003 | 7/2/2003 | 7/2/2003 | A | PASS |
Troy Cobbley
|
|
|
per letter of agreement signed by DM, FD approval granted to postpone requirement to upgrade the fire alarm system until the next tenant or March 1, 2004, whichever is earlier. S.Rogers
|
INSP-Final Inspection | 11/19/2002 | 11/20/2002 | 11/20/2002 | A | FAIL |
Troy Cobbley
|
|
|
can't give final until the ceiling tile is installed but the sprinkler piping can be covered 11/20/2002 9:03:13 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2002 | 11/18/2002 | 11/18/2002 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/15/2002 at 15:04:42. Contact: ###-####. all heads aren't Quick Response type heads as indicated on plans; one head is standard response, the others are QR type; spacing not installed per plans but meets small room 11/18/2002 2:57:28 PM
|