INSP-Final Inspection | 7/18/2003 | 7/22/2003 | 7/22/2003 | P | CANC |
Troy Cobbley
|
|
|
duplicate inspection 7/22/2003 4:28:43 PM
|
INSP-Final Inspection | 7/18/2003 | 7/18/2003 | 7/18/2003 | P | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled 7/18/2003 4:17:58 PM
|
INSP-Final Inspection | 7/16/2003 | 7/16/2003 | 7/16/2003 | P | PART |
Rick Jackson
|
|
|
need tape removed from all heads; need fire marshall tag on riser; escutcheons; sign on riser room door 7/16/2003 11:28:23 AM
|
INSP-Sprinkler Rough-in/Hydro | 7/14/2003 | 7/15/2003 | 7/15/2003 | A | PART |
Rick Jackson
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore hydro okay on both systems; need to tag system; tape/paper on some heads and escutcheons 7/15/2003 5:05:43 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/10/2003 | 7/10/2003 | 7/10/2003 | P | PART |
Troy Cobbley
|
|
|
All rough-in ok except for 12 more pendants that need cut in 7/10/2003 4:04:18 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/3/2003 | 7/3/2003 | 7/3/2003 | P | PART |
Troy Cobbley
|
|
|
items on the approved plans have been corrected in areas "C" and "D". Sprinkler rough-in in area "A" and "B" is OK
|
INSP-Supply line flush | 7/2/2003 | 7/3/2003 | 7/3/2003 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush is OK 7/3/2003 12:29:30 PM
|
INSP-Conference | 6/20/2003 | 6/23/2003 | 6/23/2003 | A | PART |
Troy Cobbley
|
|
|
supply line hydro is ok. Rough-in inspection for areas C and D are ok except for some minor problems that have been noted on the approved plans 6/23/2003 10:33:46 AM
|
INSP-Conference | 6/11/2003 | 6/12/2003 | 6/12/2003 | A | DONE |
Troy Cobbley
|
|
|
pager RUSS; Phone #: ###-#### Sprinkler pendants in the hard lid soffit areas are ok to cover. One additional pendant to be added in the soffit over the north entrance into the showroom 6/12/2003 1:05:08 PM
|
INSP-Conference | 2/10/2003 | 2/10/2003 | 2/10/2003 | P | PASS |
Troy Cobbley
|
|
|
inspection was for the remaining underground supply line that needed covering. The piping from the man hole to the interior stub-in is ok to cover 2/10/2003 3:14:23 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/6/2003 | 2/7/2003 | 2/7/2003 | P | PART |
Troy Cobbley
|
|
|
###-#### The underground supply line is OK to cover from the United Water stub-in to the concrete man hole 2/7/2003 2:22:41 PM
|